Win it. Procure it.
Control it. Get paid.

From contract award to procurement, cost control and payment, every financial workflow is connected. The bid becomes the contract sum, the award becomes the commitment, and the CVR reads itself.

Construction AI·Larkspur House › Applications › Application 4
Application 4 · Main contract
Larkspur House · valuation to 31 August · assessed by the client's QS
Construction AI
Applied
£874,316.00
this application
Certified
£0.00
awaiting assessment
Retention 3%
£0.00
held to practical completion
Net due
£0.00
final date 27 September
CodePackageContractAppliedCertified
PRELIMPreliminaries£298,412£149,206£149,206
3900General builderswork£34,320£22,300£22,300
4000Drylining£352,300£176,150£168,400
4100Suspended ceilings£252,657£63,160£63,160
5500Mechanical services£1,150,000£287,500£275,000
5600Electrical services£880,000£176,000£176,000
Assessed against the contract sum · 2 lines certified below the application, with the reasons recorded

The tools

The application above. Contract to CVR, below.

Construction AI·Larkspur House › Financial › Main Contract
Main Contract Verified
P26001 Larkspur House › Financial › Main Contract
Construction AIView contract
Contract 11Key Terms 10Pricing
Larkspur House — JCT Design and Build 2016
Larkspur House JCT DB 2016 – executed.pdf · 17.6 MB · uploaded 05/01/2026 · executed as a deed
Pages
214
Clauses
11
Key terms
10
Flags
3
Key termExtractedClause
Retention3%, half released at practical completion4.20
Interim valuationsMonthly, application on the 25th4.7
Payment notice5 days after the due date4.9
Pay less notice7 days before the final date for payment4.10
Final date for payment+14 days from the due date4.9
Liquidated damages£2,500 per week · worth a look2.29
Defects liability12 months from practical completion2.35
Contract sum£1,038,997.00 · from the bid return2
Timetable set once here and used for every valuation’s statutory dates. Ask the assistant anything the contract says.
01

The contract read once, its terms extracted, its dates set

Upload the executed contract and it is read: the clauses registered against the PDF, the key terms pulled onto their own tab, the payment timetable set once and used for every valuation’s statutory dates.

  • Retention, notices, final dates, liquidated damages and defects liability, with the clause each came from.
  • The contract sum comes from the bid return; nothing is re-keyed.
  • Ask the assistant what the contract says. It answers from the text and cites the page.
Can the AI read my contract?
Construction AI·Larkspur House › Procurement
Procurement
Larkspur House · 6 packages · 2 executed, 2 issued
Construction AI+ New
CodePackageValueTargetStatus · signature
2100Groundworks and drainage · Denham Groundworks£186,420£190,000ExecutedCompleted
3500Roofing and rainwater goods · Halliwell Roofing£109,624£112,000IssuedSent
4000Drylining · Halliwell Drylining£84,200£80,000Ready8/9 docs
5600Electrical installation · Marlow Mechanical£142,900£150,000Draft3/9 docs
3900Scaffold hire — 22 weeks · Cornfield Scaffolding£28,600IssuedSigned
1000Welfare cabins hire · Portakabin£14,300Ready3/3 docs
4000 Drylining · assembled from the tender award
Subcontract order Scope of works Pricing schedule Design responsibility matrix Attendances Payment terms Programme extract Drawings register
Buy-out target £80,000 against £84,200 offered, flagged. Send for e-signature when the ninth document is in.
02

The tender award becomes the subcontract, assembled and signed

Push the winning bidder from the tender package and everything travels: scope, pricing, design responsibility, attendances, terms. Set the buy-out target, assemble the documents, send for e-signature.

  • A buy-out above target is flagged before the order goes out.
  • The subcontract raises the commitment in the purchase ledger the moment it is executed.
  • Signature state on the register: sent, signed, completed.
How procurement works
Construction AI·Larkspur House › Purchase Ledger
Purchase Ledger
Larkspur House · nested view
Construction AIExport+ New commitment
Committed
£0.00
5 commitments
Costs to date
£0.00
7 costs against them
Paid
£0.00
costs at paid
Remaining
£0.00
committed − costs to date
Records
12
commitments and their costs
RecordRefDescriptionCommittedCostStatus
SubcontractPL-001Electrical installation — Marlow Mechanical£561,700Committed
SubcontractPL-006Application 1 — first fix to level 3£93,411Paid
SubcontractPL-009Application 2 — first fix L4–L6, second fix L1£118,738Submitted
SubcontractPL-012Application 3 — second fix L3–L4£47,433Draft
PurchasePL-002Plasterboard and fixings, phases 1–2£20,078Committed
PrelimPL-003Welfare cabins hire, 36 weeks£14,300Committed
StaffPL-004Project manager — site based£50,400Committed
A cost only ever emanates from a commitment: reference, cost code, retention and CIS come from it, never typed again. Synced to your accounts.
03

A cost only ever comes from a commitment

Commitments first: subcontract, purchase, prelim, staff. Every cost is raised against one, inheriting its reference, cost code, retention and CIS. What is committed, costed, paid and remaining reads on one screen.

  • Subcontract applications, supplier invoices and timecard hours all land here as costs.
  • Locked once committed; admin unlock with a recorded reason.
  • Synced to your accounts, with the supplier mapping shown per row.
Does this replace accounting software?
Construction AI·Larkspur House › CVR
Cost Value Reconciliation
Larkspur House · snapshot 31 Aug 2026
Construction AISnapshot now
Value
£3,861,840.00
contract sum by cost code
Total value
£0.00
revised + variations
Total cost
£0.00
cost + forecast to complete
Margin
£0.00 · 0.0%
value − total cost
CodeDescriptionTotal valueCost to dateTotal costOver/(under)
1000Preliminaries£490,440£412,900£478,500£11,940
2000Groundworks£639,150£583,420£607,400£31,750
3000Concrete frame£1,402,500£1,296,500£1,385,600£16,900
4000Drylining£433,000£396,240£424,600£8,400
5600Electrical£635,680£561,700£637,900(£2,220)
7000Roofing£358,900£341,280£352,100£6,800
Totals6 cost codes · vars £97,830£3,959,670£3,592,040£3,886,100£73,570
Value from the bid return, cost from the ledger, variations from the register. 5600 Electrical is over: Marlow’s application 2 carries an unpriced SI.
04

Value against cost, by cost code, from the records already there

The CVR is not typed. Value comes from the contract sum and the variation register, cost from the ledger and the forecasts, and the margin by cost code updates as they do. Snapshot it monthly and read the movement.

  • Budget transfers between cost codes, netting to zero, applied and locked.
  • Over and under by line, with the reason one click away.
  • The AI report explains the movement since last month, and cites it.
How the CVR is populated

0

Financial Tools

0

Years of Commercial Experience

0%

UK Construction Focused

£0

From, Per Month

Questions

How does the CVR get populated?
The value side is pre-populated from Bid Return when you push your bid. The cost side comes from procurement when subcontracts are committed and purchase ledger entries are raised. Upstream variations feed from the cost report, downstream from the variation register. Actuals come from the purchase ledger. Every number traces back to its source.
Can the AI read my contract?
Yes. Upload the contract PDF and OCR identifies key sections, extracting terms onto a dedicated tab. The contract is also chunked, embedded, and made searchable by AI. Ask about payment terms, defects liability, or liquidated damages — it searches by meaning and gives accurate answers grounded in your contract.
How do variations flow through the system?
Raise a CCI or RFC in communications. It appears in the cost report. Associated Subcontractor Instructions populate the variation register automatically. Price the variation upstream for the client. If the sub has priced their SI, pull their pricing into your sheet. Both feed into the CVR automatically. No manual logging.
How does procurement work?
Select a winning bidder in Tender Packages and push them to procurement. Everything travels — tender documents become numbered PDFs in the subcontract assembly. Set your buyout target, adjust pricing, generate AI-completed particulars, compile the document, and send for e-signature via SignWell.
How are payment applications managed?
Applications are auto-provisioned from their respective contracts. Set your payment cycle configuration — dates, terms, notice periods aligned with the Construction Act — hit generate, and every application in the cycle is created. Complete each one as it becomes due. The dashboard shows AI-generated cash flow forecasts.
Does this replace accounting software?
No. It connects to your existing accounting software. Costs and payments sync with your accounts. No double entry. The platform handles the construction-specific commercial workflows — CVR, variations, procurement — and your accounting software handles the books.