Dayworks are where honest money quietly disappears. Here's how to record daywork so it survives the QS's red pen — and actually gets paid.
Some work can't be priced from the contract. The client asks you to break out an unexpected slab you found under the floor. There's no rate for it, no quantity, and no time to agree one before the gang's stood there waiting. So you do it on daywork — you record the labour, plant and materials it actually took, and you recover the cost.
That's what daywork is for: work that can't reasonably be valued using the contract rates. Used properly, it's a fair mechanism that protects both sides. Used carelessly — which is most of the time — it's the single biggest source of unrecovered cost on a small contractor's job. The work gets done, the money gets spent, and three months later the daywork claim gets rejected because nobody signed the sheet.
I've watched contractors carry thousands of pounds of genuine daywork cost purely because the paperwork wasn't there. The work was real. The cost was real. The recovery was zero. Let's fix that.
Daywork is a method of last resort, not a first choice. Most contracts make this explicit: work should be valued using the contract rates and prices where possible, similar rates where the work is comparable, and daywork only where the work can't properly be valued any other way.
That matters, because a QS will always try to value your extra work by measure first — it's usually cheaper for the client. If you've booked something as daywork that could have been measured against a rate, expect it to be challenged. Daywork genuinely applies when:
If the work fits a rate, use the rate. Save daywork for the things that genuinely don't.
Daywork is valued on the actual resources used — the prime cost — plus percentage additions. In UK practice this usually follows a recognised basis (many contracts reference the RICS/industry Definition of Prime Cost of Daywork carried out under a Building Contract), or the percentages written into your contract's daywork schedule. The three components:
The percentages are where money is won and lost, and they should have been fixed at tender — check what you signed up to. If your daywork percentages are thin, that's a tender lesson for next time; for now, the priority is recovering the prime cost you can prove.
Here's the uncomfortable truth: a daywork claim is only as good as the sheet behind it. Everything else is secondary. So treat the sheet as the deliverable, not an afterthought.
A daywork sheet needs to record, at the time the work is done:
Then get it signed. This is the part people skip, and it's the part that decides whether you get paid.
Understand the distinction, because it catches people out. When the client's representative signs your daywork sheet, they may be doing one of two things:
Most CAs will only sign "for record purposes," and that's fine — it still verifies your resources, which is 90% of the battle. What you must not do is fail to get a signature at all. An unsigned daywork sheet submitted weeks later, with no contemporaneous verification, is the easiest thing in the world for a QS to reject: "I can't verify these hours, I wasn't there, I'm not paying them." Get the signature at the time, whatever basis it's on, and your evidence is intact even if the principle is still in play.
The failures are boringly consistent, which is good news — they're all avoidable:
Every one of these is a paperwork failure, not a work failure. Which means every one of them is preventable at zero cost.
At Construction AI, daywork is captured against the instruction that triggered it — labour, plant and materials recorded on site, linked to the variation or RFI, backed by the site diary and photos from the same day. When it flows into the payment application, the record is already assembled — instruction, resources, evidence, date — rather than reconstructed from memory the week before the final account. The daywork you can prove is the daywork you get paid for.
Daywork is fair money for real work. But the industry loses more of it to bad paperwork than to genuine dispute. Write the sheet at the time, tie it to the instruction, get it signed for whatever it's worth, and keep the evidence together. Do that and the honest money stops disappearing.
What is daywork in construction?
Daywork is a method of valuing work based on the actual labour, plant, and materials used (the prime cost), plus percentage additions — used when the work can't reasonably be valued using the contract rates.
When should work be valued as daywork?
Only when it can't properly be valued by the contract rates or analogous rates — typically unforeseen, unmeasurable, or disruptive work carried out under instruction with no opportunity to agree a price first. If a rate fits, the rate should be used.
What should a daywork sheet include?
The instruction reference, date and location, labour (names, trades, hours), plant used and duration, materials and quantities, and a description of the work and why it couldn't be measured — recorded at the time and signed by the client's representative.
What's the difference between signing a daywork sheet "as agreed" and "for record purposes"?
Signing as agreed accepts the work as daywork with resources agreed. Signing for record purposes only verifies the hours and resources were as stated, while reserving the right to dispute whether it should be daywork. Either way, get the signature at the time — it verifies your resources.
Why do daywork claims get rejected?
Almost always for paperwork reasons: no signed sheet, sheets submitted late, work that should have been measured, vague descriptions, or no link to an authorising instruction — not because the work wasn't done.
Stephen Mckenna MCIOB
30+ years in UK commercial construction, from site management to director level. Now building the project management tools he wished he'd had.
Tier-one contractor processes shouldn't only be available to tier-one contractors. Drawing registers, document control, RFIs, programmes, financial tracking — built for how you actually run projects, priced so any construction business can access them. Try everything free for 30 days.
By subscribing, you agree to our Privacy Policy.
The government has confirmed it's banning cash retentions in construction. Here's what the Commercial Payments Bill actually changes, when, and what to do about your cash flow now.
Under-measure and you're funding the client's project. Over-measure and you'll pay it back with interest. Here's how to value work in progress accurately, every month.
Profitable projects still go bust — because profit isn't cash. Here's how to forecast a project's cash position with an S-curve and see the squeeze before it happens.
Tier-one processes, priced for any size business. Try everything free for 30 days — no charge until your trial ends.