Attendances decide who provides each site facility a subcontractor relies on. Get them vague and you pay twice or fight about it later. Here's how to set attendances out clearly at tender and make them stick on site.
Every subcontract package relies on things nobody prices in the main scope. The dryliner needs power within reach of the work. The M&E contractor needs their pipework lifted to the third floor. The cladder needs a scaffold that's adapted as they go. Everybody needs toilets, a canteen, somewhere to store materials and a skip.
Somebody has to provide each of those. If the enquiry doesn't say who, two things happen. Either the subcontractor prices it and so do you, and the client pays twice. Or neither of you prices it, and it becomes a row on site — usually the week a crane's booked.
That's what attendances are for. An attendance schedule says, for each facility, who provides it. It's one of the least exciting documents in a tender and one of the most argued-about once work starts.
The old Standard Method of Measurement split attendances into two kinds, and most contractors still use the words:
The labels matter less than the principle: if it's provided for one trade, say so and say who pays. "General attendance included" on its own tells a subcontractor very little.
These are the attendances that come up again and again on site. Each one needs an explicit answer in the schedule:
The clearest way to set out attendances is a matrix. One row per facility. For each row, say who provides it and who supports it:
| Facility | Main contractor | Subcontractor | Notes |
|---|---|---|---|
| Welfare and messrooms | Provides | — | For up to 20 operatives |
| 110V power | Provides | Leads and transformers from the distribution point | Within 25m of the work area |
| Hoisting | Provides | Labour to load | Tower crane by booking, 4 hours a week |
| Waste | Skips | Clears own waste to skips daily | Segregated |
| Scaffolding | Standing scaffold | Requests adaptations in writing, 48 hours' notice | Adaptations charged unless listed |
A matrix does three things a paragraph can't. It forces an answer for every facility. It's easy for tenderers to price against. And it's easy to check on site when someone says "that's not ours".
The attendance schedule belongs in the enquiry pack, alongside the scope of works, the drawings and the programme. Ask every tenderer to price against it and to qualify anything they don't accept.
Then, when you compare bids, check the qualifications against the matrix. A subcontractor who has excluded hoisting is cheaper on paper, but you'll be paying for the crane time. Level those exclusions before you compare totals.
The schedule that was issued at tender, updated for anything agreed during clarifications, has to go into the subcontract order. It's surprising how often it doesn't — the order refers to "attendances as discussed", and the discussion isn't written down anywhere.
If it's not in the subcontract, it's not enforceable. And when there's a disagreement on site, the first question will be what the subcontract says.
The site team should know what each subcontractor's attendances are without digging out the tender file. When a subcontractor asks for something outside their attendances — an extra scaffold lift, more crane time, a dedicated power supply — that's a request to record and price, not a favour to do quietly. When a subcontractor fails to provide what they're responsible for — clearing their waste, protecting their own work — and you have to do it, that's a contra charge, but only if the attendance was clear in the first place.
At Construction AI, attendances are a Library matrix: for each site facility — welfare, power, hoisting, scaffold and the rest — who provides it and who supports it, saved once and reused on every package. Describe the trade and the AI drafts the matrix, and you tick which rows to keep. The matrix goes out as part of the tender enquiry pack alongside the scope, the design responsibility matrix and the payment schedule, exports to Excel, and is generated into the subcontract pack when the winner is chosen — so the attendances the subcontractor priced are the ones in their contract.
Attendances are never the interesting part of a tender. But a clear matrix, priced against and carried into the order, takes a whole category of site arguments off the table.
What are attendances in construction?
Attendances are the facilities and services a main contractor provides — or doesn't — to support a subcontractor's work: things like welfare, power, lighting, water, scaffolding, hoisting, storage, waste removal and unloading. An attendance schedule sets out who provides each one, so it's priced once and not argued about later.
What is the difference between general and special attendance?
General attendance covers the shared facilities already on site that a subcontractor can use, such as welfare, existing scaffolding, temporary lighting, water and rubbish removal. Special attendance covers facilities provided specifically for one trade, such as dedicated scaffolding or access, unloading and hoisting their materials, or specific storage and power. The terms come from the old standard method of measurement and are still widely used.
Why do attendances cause disputes?
Because they're often left vague in the enquiry. The subcontractor assumes the main contractor provides something; the main contractor assumes the subcontractor priced it. Either it's paid for twice, or it isn't priced at all and becomes an argument — and sometimes a contra charge — on site.
Should attendances be in the subcontract order?
Yes. The attendance schedule issued at tender should be carried into the subcontract, updated for anything agreed during tender clarification. If it isn't in the subcontract, it isn't enforceable when there's a disagreement on site.
How do I set out attendances clearly?
Use a matrix: one row per facility, and for each one say whether the main contractor provides it, the subcontractor provides it, it's shared, or it doesn't apply — with a note for limits such as distances, hours or quantities. Issue it with the enquiry, ask tenderers to price and qualify against it, and carry it into the order.
Stephen Mckenna MCIOB
30+ years in UK commercial construction, from site management to director level. Now building the project management tools he wished he'd had.
Tier-one contractor processes shouldn't only be available to tier-one contractors. Drawing registers, document control, RFIs, programmes, financial tracking — built for how you actually run projects. One platform, every module, every user — priced to your business. Leave your email and we'll show you round.
By subscribing, you agree to our Privacy Policy.
A UK comparison of construction estimating and quantity take-off software — Construction AI, RIB CostX, Causeway Estimating, Access ConQuest, Bluebeam Revu, Kreo and Togal.AI — on CAD and BIM take-off, AI, rate build-ups, subcontract tendering and what happens after the estimate.
Measuring a PDF gives you a scaled estimate. Measuring the CAD file gives you the designer's own figures. Here's what each is good for, where CAD take-off goes wrong, and how to get the files in the first place.
The cheapest way to lose money is to win a job on someone else's terms. Qualifications are how you price what's in front of you, not what they hope you'll swallow.
Tier-one processes for the whole business. One platform, every module, every user, priced to your business.