Attendances: Who Provides the Scaffold, the Power and the Welfare?

Attendances decide who provides each site facility a subcontractor relies on. Get them vague and you pay twice or fight about it later. Here's how to set attendances out clearly at tender and make them stick on site.

SMStephen Mckenna MCIOB
6 minutes read

Attendances: Who Provides the Scaffold, the Power and the Welfare?

Every subcontract package relies on things nobody prices in the main scope. The dryliner needs power within reach of the work. The M&E contractor needs their pipework lifted to the third floor. The cladder needs a scaffold that's adapted as they go. Everybody needs toilets, a canteen, somewhere to store materials and a skip.

Somebody has to provide each of those. If the enquiry doesn't say who, two things happen. Either the subcontractor prices it and so do you, and the client pays twice. Or neither of you prices it, and it becomes a row on site — usually the week a crane's booked.

That's what attendances are for. An attendance schedule says, for each facility, who provides it. It's one of the least exciting documents in a tender and one of the most argued-about once work starts.

General and special attendance

The old Standard Method of Measurement split attendances into two kinds, and most contractors still use the words:

  • General attendance — the shared facilities already on site that any subcontractor can use. Welfare and messrooms, existing scaffolding as it stands, temporary lighting and water, clearing away rubbish, space for site huts and storage.
  • Special attendance — facilities provided specifically for one trade. Dedicated or adapted scaffolding, access roads or hardstandings for their plant, unloading, distributing and hoisting their materials, specific storage, or a dedicated power supply.

The labels matter less than the principle: if it's provided for one trade, say so and say who pays. "General attendance included" on its own tells a subcontractor very little.

The facilities that cause most arguments

These are the attendances that come up again and again on site. Each one needs an explicit answer in the schedule:

  • Scaffolding and access. Is the subcontractor using the scaffold as it stands, or do they need adaptations, extra lifts or loading bays? Who provides MEWPs, towers and podiums? Who inspects them?
  • Hoisting and unloading. Crane time, hoist time and labour to unload. Who books the crane, and how many hours are included?
  • Power and lighting. 110V supply within what distance of the work? Task lighting or just general lighting? Who provides transformers, leads and distribution boards for the trade?
  • Water. Supply points, and who provides hoses, bowsers or pressure testing water.
  • Welfare. Canteen, toilets, drying rooms. Usually provided, but say so — especially if the subcontractor's numbers peak.
  • Storage and laydown. Space, secure containers, protection from weather. Who's responsible if materials are stolen or damaged?
  • Waste. Skips, segregation, and who clears the subcontractor's waste to the skip. "Clean as you go" needs saying.
  • Protection of finished work. Who protects floors, frames and finishes once installed, and who pays when they're damaged by someone else?
  • Setting out. Main grid lines and levels by the main contractor; trade setting out by the subcontractor? Write it down.
  • Testing and commissioning. Attendance during testing, temporary power for commissioning, and who witnesses it.
  • Temporary works and fire precautions. Hot works permits, fire extinguishers, edge protection, and who removes and reinstates it.

Use a matrix, not a paragraph

The clearest way to set out attendances is a matrix. One row per facility. For each row, say who provides it and who supports it:

FacilityMain contractorSubcontractorNotes
Welfare and messroomsProvides—For up to 20 operatives
110V powerProvidesLeads and transformers from the distribution pointWithin 25m of the work area
HoistingProvidesLabour to loadTower crane by booking, 4 hours a week
WasteSkipsClears own waste to skips dailySegregated
ScaffoldingStanding scaffoldRequests adaptations in writing, 48 hours' noticeAdaptations charged unless listed

A matrix does three things a paragraph can't. It forces an answer for every facility. It's easy for tenderers to price against. And it's easy to check on site when someone says "that's not ours".

At tender: issue it, then level against it

The attendance schedule belongs in the enquiry pack, alongside the scope of works, the drawings and the programme. Ask every tenderer to price against it and to qualify anything they don't accept.

Then, when you compare bids, check the qualifications against the matrix. A subcontractor who has excluded hoisting is cheaper on paper, but you'll be paying for the crane time. Level those exclusions before you compare totals.

In the subcontract: carry it across

The schedule that was issued at tender, updated for anything agreed during clarifications, has to go into the subcontract order. It's surprising how often it doesn't — the order refers to "attendances as discussed", and the discussion isn't written down anywhere.

If it's not in the subcontract, it's not enforceable. And when there's a disagreement on site, the first question will be what the subcontract says.

On site: hold people to it

The site team should know what each subcontractor's attendances are without digging out the tender file. When a subcontractor asks for something outside their attendances — an extra scaffold lift, more crane time, a dedicated power supply — that's a request to record and price, not a favour to do quietly. When a subcontractor fails to provide what they're responsible for — clearing their waste, protecting their own work — and you have to do it, that's a contra charge, but only if the attendance was clear in the first place.

How Construction AI handles it

At Construction AI, attendances are a Library matrix: for each site facility — welfare, power, hoisting, scaffold and the rest — who provides it and who supports it, saved once and reused on every package. Describe the trade and the AI drafts the matrix, and you tick which rows to keep. The matrix goes out as part of the tender enquiry pack alongside the scope, the design responsibility matrix and the payment schedule, exports to Excel, and is generated into the subcontract pack when the winner is chosen — so the attendances the subcontractor priced are the ones in their contract.

Attendances are never the interesting part of a tender. But a clear matrix, priced against and carried into the order, takes a whole category of site arguments off the table.

Frequently asked questions

What are attendances in construction?

Attendances are the facilities and services a main contractor provides — or doesn't — to support a subcontractor's work: things like welfare, power, lighting, water, scaffolding, hoisting, storage, waste removal and unloading. An attendance schedule sets out who provides each one, so it's priced once and not argued about later.

What is the difference between general and special attendance?

General attendance covers the shared facilities already on site that a subcontractor can use, such as welfare, existing scaffolding, temporary lighting, water and rubbish removal. Special attendance covers facilities provided specifically for one trade, such as dedicated scaffolding or access, unloading and hoisting their materials, or specific storage and power. The terms come from the old standard method of measurement and are still widely used.

Why do attendances cause disputes?

Because they're often left vague in the enquiry. The subcontractor assumes the main contractor provides something; the main contractor assumes the subcontractor priced it. Either it's paid for twice, or it isn't priced at all and becomes an argument — and sometimes a contra charge — on site.

Should attendances be in the subcontract order?

Yes. The attendance schedule issued at tender should be carried into the subcontract, updated for anything agreed during tender clarification. If it isn't in the subcontract, it isn't enforceable when there's a disagreement on site.

How do I set out attendances clearly?

Use a matrix: one row per facility, and for each one say whether the main contractor provides it, the subcontractor provides it, it's shared, or it doesn't apply — with a note for limits such as distances, hours or quantities. Issue it with the enquiry, ask tenderers to price and qualify against it, and carry it into the order.

SM

Stephen Mckenna MCIOB

30+ years in UK commercial construction, from site management to director level. Now building the project management tools he wished he'd had.

Stop losing money on problems you can see coming

Tier-one contractor processes shouldn't only be available to tier-one contractors. Drawing registers, document control, RFIs, programmes, financial tracking — built for how you actually run projects. One platform, every module, every user — priced to your business. Leave your email and we'll show you round.

By subscribing, you agree to our Privacy Policy.

Run the next job on it.

Tier-one processes for the whole business. One platform, every module, every user, priced to your business.