Run the job

Your planner’s file, on a real scheduling engine.

Bring in the P6, Asta or MS Project file. Float and the critical path are recalculated after every save, every change arrives as a set you apply or reject, and the issued programme is never edited directly.

Book a demo
Construction AI·Larkspur House › Programme
Programme
Project schedule and Gantt chart • 0 tasks
Construction AI
+Week ▾⚠ Critical PathBaselinesExport
WBSTask NameStart%
1PHASE 1: MOBILISATION01 Sep
1.1Possession and set-up01 Sep100%
2PHASE 2: STRIP OUT08 Sep
2.1Strip-out, levels 1–308 Sep0%
3PHASE 3: PLANT DECK15 Sep
3.1Plant deck steelwork15 Sep0%
3.2AHU lifts and installation13 Oct0%
4PHASE 4: FIT-OUT29 Sep
4.1Partitions and ceilings29 Sep0%
4.2Raised access floors27 Oct0%
4.3M&E first and second fix03 Nov0%
4.4Finishes and decorations14 Dec0%
5Commissioning and handover25 Jan0%
6Practical completion01 Mar
Sep 2026
Oct
Nov
Dec
Jan 2027
Feb
W36
W40
W44
W48
W52
W4
W8
PHASE 1: MOBILISATION
Possession and set-up
PHASE 2: STRIP OUT
Strip-out
PHASE 3: PLANT DECK
Plant deck steelwork
AHU lifts and installation
PHASE 4: FIT-OUT
Partitions and ceilings
Raised access floors
M&E first and second fix
Finishes and decorations
Commissioning and handover

The tools

From the file that arrives to the update you issue.

Construction AI·Larkspur House › Programme
Programme
Project schedule and Gantt chart • 14 tasks
Construction AI
+Week ▾⚠ Critical PathBaselinesExport
WBSTask NameStart%
1PHASE 1: MOBILISATION01 Sep
1.1Possession and set-up01 Sep100%
2PHASE 2: STRIP OUT08 Sep
2.1Strip-out, levels 1–308 Sep0%
3PHASE 3: PLANT DECK15 Sep
3.1Plant deck steelwork15 Sep0%
3.2AHU lifts and installation13 Oct0%
4PHASE 4: FIT-OUT29 Sep
4.1Partitions and ceilings29 Sep0%
4.2Raised access floors27 Oct0%
4.3M&E first and second fix03 Nov0%
4.4Finishes and decorations14 Dec0%
5Commissioning and handover25 Jan0%
6Practical completion01 Mar
Sep 2026
Oct
Nov
Dec
Jan 2027
Feb
W36
W40
W44
W48
W52
W4
W8
PHASE 1: MOBILISATION
Possession and set-up
PHASE 2: STRIP OUT
Strip-out
PHASE 3: PLANT DECK
Plant deck steelwork
AHU lifts and installation
PHASE 4: FIT-OUT
Partitions and ceilings
Raised access floors
M&E first and second fix
Finishes and decorations
Commissioning and handover
01

A full planning tool, in the browser

Calendars with bank holidays and shutdowns, baselines under the bars, saved views, code libraries for zone, phase and trade, and resource levelling.

  • Imports from Primavera P6, Asta Powerproject and MS Project.
  • Goes out as P6, MS Project, Excel, PDF and print-ready A3 or A1.
  • A line-of-balance view, with clash flags.
Construction AI·Larkspur House › Programme › Integrity check
Integrity check
Larkspur House programme · run on import · revision D
Construction AI3 to look at
CheckFoundResult
Activities with no predecessor1The start only
Activities with no successor21 open end
Logic loops0None
Long lags3Over 10 days
Fixed dates14.4 Finishes
Negative float0None
The check runs by itself each time a programme comes in. Health, delayed activities and a forecast of completion can be asked for at any time.
02

Checked the moment it comes in

An integrity check runs by itself on every import: open ends, loops, long lags, fixed dates and negative float.

  • Ask for the programme’s health at any time.
  • Delayed activities and risks are found for you.
  • A weekly programme report on request.
Construction AI·Larkspur House › Programme › Working copy
Change set
Working copy of revision D · proposed, not applied
RejectApply
Proposed change, and whyEffect
Split 4.1 Partitions into level 1 and level 2. Level 2 ceiling grid information is late.Completion 17 Mar to 12 Mar
Start 4.3 first fix on level 1 while level 2 waits. Uses the gang already on site.Float on 4.3: 0 to 4 days
Add 3 days after 3.2 AHU lifts. Crane permit.No change to completion
Proposed by
The assistant, asked by Sam Okafor on 2 Dec. The programme the client issued is untouched until you apply the set, and Undo puts it back.
The assistant only proposes. A set is refused if the programme has moved since it was proposed.
03

Nothing changes until you apply it

The programme the client issued is never edited directly. You work on a copy, and every change, yours or the assistant’s, arrives as a set with its reason and its effect.

  • Apply, reject or undo.
  • The assistant only proposes; a person applies.
  • A set is refused if the programme has moved since it was proposed.
Construction AI·Larkspur House › Programme › Value
Value curve
Larkspur House · the contract sum spread on the programme
Construction AIExport
Planned to date
£412,000
at 30 Nov
Earned
£388,500
from progress
Applied for
£395,200
3 applications
Certified
£371,900
by the client
PlannedEarnedApplied forCertified
04

The contract sum, spread on the programme

Spread the contract sum onto the activities and get a value curve and earned value, against what has been applied for and certified.

  • Progress can come from the site records.
  • Group the programme by cost code.
  • What-if a delay, and see the completion forecast.
Construction AI·Larkspur House › Programme › Windows
Windows
Larkspur House · what moved completion at each update
Construction AIEOT submission
Win.UpdateCompletionMovedDriven by
W101 Sep01 Mar—Baseline accepted
W230 Sep04 Mar+3 dDE-001 reception bulkhead
W331 Oct09 Mar+3 dDE-002 RFI #004 answered late
W430 Nov17 Mar+6 dDE-003 asbestos, riser 2
Completion, update by update01 Mar to 17 Mar
W1
W2
W3
W4
Worked out from the record by rule. Every judgement in the submission is written and signed by a person.
05

What moved between one update and the next

Lettered revisions can be compared, restored, accepted as the baseline or laid over the bars. At each status date you see what drove completion.

  • Float gained and lost in each window.
  • What slipped, and what was added or removed.
  • Activities are matched across re-imports, even when renumbered.

Questions

Which programme files can I bring in?
Primavera P6 (.xer), Asta Powerproject (.pp) and MS Project (.mpp and XML), with their calendars and code libraries.
Can I send it back to the planner in Asta?
Asta files come in. Programmes go back out as P6 or MS Project files, and as Excel and PDF.
Will the AI change my programme?
No. It proposes changes as a set, with the reason and the effect of each. A person applies them, and they can be undone.
Can it write a programme from scratch?
Yes. A complete programme, with its work breakdown and logic, can be generated for you to check and change.

Bring a programme.

Send us a P6, Asta or MS Project file. We will open it on a demo call and show you what it is telling you.