Run the job

The letter is where the variation starts.

Formal letters, site instructions, requests for change and for price, and confirmations of client instruction. Issuing one raises the variation, instructs the trade and links the drawings it relies on.

Book a demo
Construction AI·Larkspur House › Correspondence
Correspondence
Larkspur House · letters, instructions and requests
Construction AI+ New
RefSubjectReplyState
CCI-007Reception bulkhead and feature ceiling16 SepVariation raised
RFC-012Additional comms room, level 319 SepWith the client
SI-019Reception bulkhead, to Halliwell Drylining—Issued to the trade
RFP-011Fire-stopping, riser 212 SepAwaiting price
L-042Request for an updated design programme10 SepReply overdue
Letters, site instructions, requests for change, requests for price and confirmations of client instruction, each with its own numbering and distribution.

The tools

From the letter to the cost report, without logging it twice.

Construction AI·Larkspur House › Correspondence
Correspondence
Larkspur House · letters, instructions and requests
Construction AI+ New
RefSubjectReplyState
CCI-007Reception bulkhead and feature ceiling16 SepVariation raised
RFC-012Additional comms room, level 319 SepWith the client
SI-019Reception bulkhead, to Halliwell Drylining—Issued to the trade
RFP-011Fire-stopping, riser 212 SepAwaiting price
L-042Request for an updated design programme10 SepReply overdue
Letters, site instructions, requests for change, requests for price and confirmations of client instruction, each with its own numbering and distribution.
01

Every formal letter, by kind

Letters, site instructions, requests for change, requests for price and confirmations of client instruction, each with a reference, a distribution list and a reply-due date.

  • Linked drawings and specification clauses.
  • External parties can reply.
  • What is overdue is shown as overdue.
Construction AI·Larkspur House › Correspondence › L-043
L-043 Draft
To Laird Studio · drafted from the thread on L-042
Construction AIApply to editor

Larkspur House: design programme

We refer to our letter L-042 of 3 September asking for an updated design programme, to which we have not had a reply.

The ceiling grid information for level 2 was due on 1 September and is now holding the partitions on that level. Please issue the programme, with a date for that information, by 17 September.

We will record the effect on the works in the usual way.

Written from
L-042 and its threadA-2401 rev DRFI #004
Ask for a letter in words, or for a reply to the thread. You edit it and you send it.
02

Ask for the letter. Edit it. Send it.

Ask for “a formal letter requesting an updated programme” and it is drafted from the documents attached. A reply is drafted from the thread.

  • Written in the language a contract letter needs.
  • It names the records it was written from.
  • Nothing goes out until you send it.
Construction AI·Larkspur House › Correspondence › CCI-007
CCI-007 Confirmation of client instruction
Larkspur House › Correspondence · to the employer’s agent · reply due 16 Sep
Construction AIIssue
Northgate Contracts · letter
Reception bulkhead and feature ceiling

We confirm your instruction at the site meeting of 2 September to form a bulkhead and feature ceiling raft to reception, as marked on drawing A-2301 rev C.

This is a change to the Employer’s Requirements. We will price it and notify any effect on the completion date.

Cost code 4000Distribution: 4
What issuing this does
Variation CCI-007 added to the cost report
cost code 4000 Drylining · state Budget until priced
Site instruction SI-019 issued to Halliwell Drylining
on the subcontract variation register
Request for price RFP-011 sent with it
their build-up comes back against your assessment
Linked to what it relies on
drawing LH-LRD-ZZ-01-DR-A-2301 rev C · RFI #004
Void the letter and you are shown what comes off the cost report before it does.
03

Confirm the instruction and the variation exists

A confirmation of client instruction or a request for change creates the variation in the cost report, on the cost code the letter names.

  • A request for change converts to an instruction when the client agrees.
  • The drawings it relies on are linked.
  • The variation starts as a budget until it is priced.
Construction AI·Larkspur House › Subcontract variations
Subcontract variations
4000 Drylining · Halliwell Drylining · site instructions, requests for price and their own
Construction AI+ Site instruction
RefVariationTheirsYoursState
SI-019Reception bulkhead · CCI-007£9,245£9,245Agreed
SI-021Acoustic upgrade · CCI-011£4,860£4,120Assessed
RFP-011Fire-stopping, riser 2 · asked 4 Sep—Awaiting price
DOM-03Extra bulkhead · theirs£3,900Not evidenced
DOM-04Out-of-sequence work · theirs£2,150Query sent
DOM-03 · why your figure is blank
No site instruction, drawing revision or diary entry on record for a second bulkhead. Left blank with the reason, not set to zero. A query has gone to Halliwell from this line.
Subcontractors raise their own variations in the portal. The assistant proposes your assessment line by line and never alters their claim.
04

The site instruction goes to the subcontractor

A site instruction fans out to the subcontract variation register, so the trade is instructed and their side of the variation is open.

  • Requests for price go out the same way.
  • Their build-up sits beside your assessment.
  • It is grouped by package.
Construction AI·Larkspur House › Correspondence › CCI-007
Void CCI-007?
What voiding this letter will do, shown before you do it
CancelVoid the letter
On the cost reportEffect
Variation CCI-007Removed · your price £11,200
Projected final account£3,959,670 becomes £3,948,470
Account maturityOne firm variation fewer
CCI-007
Reception bulkhead and feature ceiling. Confirmed to the employer’s agent on 2 September.
A letter that raised a variation cannot be voided blind. You see what comes off the cost report first.
05

See what voiding a letter will do, first

Before a letter that raised a variation is voided, you are shown what it will take off the cost report.

  • No variation disappears by accident.
  • The projected final account before and after.
  • You can still cancel.

Questions

What kinds of letter does it handle?
Formal letters, site instructions, requests for change, requests for price and confirmations of client instruction, each numbered in its own series.
Does issuing an instruction really create the variation?
Yes. A confirmation of client instruction or a request for change creates the variation in the cost report, and a site instruction goes to the subcontract variation register.
Does the AI send letters?
No. It drafts a letter or a reply for you to edit. A person sends it.
What if I void a letter by mistake?
You are shown what voiding it will take off the cost report before you confirm.

Issue your next instruction from it.

Tell us about a live job. We will confirm an instruction and follow it into the cost report on a demo call.