Every bid on the same lines. The winner becomes the subcontract.

Returns land against the schedule you priced from. Gaps, outliers and qualifications are found, queries go out and come back, and the price you level is the price on the subcontract.

Book a demo
Construction AI·Larkspur House › Tender packages › 4000 › Analysis
4000 — Drylining
Larkspur House · bid levelling · 3 returns
Construction AIExport bid tab
StageHalliwellApexNorton & Bell
Base bid£352,300£331,150£383,400
Tender query adjustments—+ £24,600− £8,200
General adjustments− £2,300——
Final adjusted bid£350,000£355,750£375,200
Priced by them, not on your schedule · left out by them
Apex InteriorsFire-stopping to compartment lines left out
Norton & BellAdded: out-of-hours working, £8,200
The lowest is marked at each stage. The cheapest base bid is not the cheapest bid once what it left out is priced.

The tools

From three returns to one signed subcontract.

Construction AI·Tender package 4000 › Compare
4000 — Drylining
Larkspur House · Tender package · Bid comparison · returns 3 of 4
Tender AnalysisConstruction AI
InviteesCompareAnalysis
ItemDescriptionHalliwell DryliningApex InteriorsNorton & Bell
4000.1Metal stud partitions, levels 1–3£182,400£176,900£214,200
4000.2MF ceilings and bulkheads£96,300£101,800£94,750
4000.3Fire-stopping to compartment lines£24,100excluded£26,800
4000.4Acoustic upgrades, meeting rooms£31,500£29,950£30,400
4000.5Attendances and preliminaries£18,000£22,500£17,250
Return total£352,300£331,150£383,400
In lineQuery raisedOutlier
3 queries raisedFinal analysis£0.00
Tender queries · drafted from the comparisonSend to bidders
4000.1Norton & BellPartitions 17% above the other returns: confirm the specification allowed for (BS EN 520 board, 70 mm stud).Outlier
4000.3Apex InteriorsFire-stopping excluded: price the compartment lines on drawing 03001 or confirm the exclusion stands.Outlier
4000.5Apex InteriorsAttendances 25% above the others: confirm what the sum covers beyond the preliminaries listed.Query
01

Returns compared line by line

Each bid lands against the schedule you priced from, so like is compared with like. Every figure is flagged against the others.

  • Green, amber and red against every figure.
  • Items a tenderer priced that were not on the schedule are shown.
  • A line left out is shown as left out.
Construction AI·Tender package 4000 › Analysis
Initial tender analysis
4000 Drylining · 3 returns · four passes
Construction AI3 queries drafted
PassWhat it foundOutcome
Rate anomaliesNorton & Bell: partitions 17% above the other two.Query drafted
GapsApex: nothing priced for fire-stopping to compartment lines.Query drafted
QualificationsNorton & Bell: normal hours only, out-of-hours extra.Query drafted
Standard termsApex: 60-day payment terms, against 30 in the enquiry.Flagged
It proposes like-for-like adjustments and never invents a figure for something a bidder left out. You tick which to apply.
02

Four passes over every return

Rate anomalies, gaps between what was asked for and what was priced, the qualifications each tenderer made, and a sense-check of their standard terms.

  • Unlisted items are grouped by what they mean, to find the gaps.
  • Queries are drafted from what it finds.
  • It never invents a figure for something a bidder left out.
Construction AI·Tender package 4000 › Tender queries
Tender queries
Apex Interiors · sent as Excel, answered in the portal
3 of 3 answered
Base bid
£331,150
as returned
Adjustment
+ £24,600
from their answers
Revised total
£355,750
confirmed by them
No.QueryTheir answer
TQ-01Confirm fire-stopping to compartment lines is included.Excluded. Add £24,600.
TQ-02Confirm payment terms as the enquiry.Accepted.
TQ-03Confirm a nine-week programme.Confirmed.
Answers come back by upload or through the portal and update the comparison.
03

Queries out, answers back, comparison updated

Each bidder gets their own query document. Answers come back by upload or through the portal, with a revised total.

  • Queries go out per bidder as Excel.
  • Their answer and revised figure update the comparison.
  • Nothing is retyped from an email.
Construction AI·Tender package 4000 › Levelling
4000 — Drylining
Larkspur House · bid levelling · 3 returns
Construction AIExport bid tab
StageHalliwellApexNorton & Bell
Base bid£352,300£331,150£383,400
Tender query adjustments—+ £24,600− £8,200
General adjustments− £2,300——
Final adjusted bid£350,000£355,750£375,200
Priced by them, not on your schedule · left out by them
Apex InteriorsFire-stopping to compartment lines left out
Norton & BellAdded: out-of-hours working, £8,200
The lowest is marked at each stage. The cheapest base bid is not the cheapest bid once what it left out is priced.
04

Four stages, with the lowest marked at each

Base bid, tender-query adjustments, general adjustments and the final adjusted bid, side by side for every tenderer.

  • Proposed adjustments are yours to tick.
  • Export an A3 bid tab as a PDF.
  • Or a levelling workbook with the line items, qualifications and queries.
Construction AI·Tender package 4000 › Winner
Winner
4000 Drylining · Larkspur House
Package closed
Winner
Halliwell
Halliwell Drylining
Final adjusted bid
£350,000
after queries
Returns
3 of 4
one did not bid
✓Package closedHalliwell Drylining selected as winner
✓Pushed to Master Pricingthe estimate now carries the winning price for 4000
✓Procurement record createdthe subcontract, with Halliwell Drylining as the party
✓Pack generated to go with itscope, design responsibility matrix, attendances, payment schedule, documents
Nothing is typed again. The price you levelled is the price on the subcontract.
05

Choosing the winner does the rest

Select the winner and the package closes. Their price goes into Master Pricing, and the procurement record is created with the pack that goes with it.

  • Scope, design responsibility, attendances, payment schedule and documents are generated as PDFs.
  • The estimate carries the price you bought at.
  • Nothing is typed again.
Construction AI·Larkspur House › Procurement
Procurement
Larkspur House · 6 packages · 2 executed, 2 issued
Construction AI+ New
CodePackageValueTargetStatus · signature
2100Groundworks and drainage · Denham Groundworks£186,420£190,000ExecutedCompleted
3500Roofing and rainwater goods · Halliwell Roofing£109,624£112,000IssuedSent
4000Drylining · Halliwell Drylining£84,200£80,000Ready8/9 docs
5600Electrical installation · Marlow Mechanical£142,900£150,000Draft3/9 docs
3900Scaffold hire — 22 weeks · Cornfield Scaffolding£28,600—IssuedSigned
1000Welfare cabins hire · Northfield Cabins£14,300—Ready3/3 docs
4000 Drylining · assembled from the tender award
Subcontract order Scope of works Pricing schedule Design responsibility matrix Attendances Payment terms Programme extract Drawings register
Buy-out target £80,000 against £84,200 offered, flagged. Send for e-signature when the ninth document is in.
06

The award is already in procurement

The subcontract exists the moment the winner is chosen, at the levelled price, ready to be assembled and signed.

  • The commitment follows from the subcontract.
  • Applications and variations hang off it from day one.
  • The pack that goes with it is already generated.

Questions

What if a bidder leaves something out?
It is shown as left out and a query is drafted. A figure is never invented for it; the bidder gives one, or you make the adjustment yourself.
Who decides which adjustments apply?
You do. Like-for-like adjustments are proposed and you tick which to apply.
Can I take the comparison to a meeting?
Yes. Export an A3 bid tab as a PDF, or an Excel levelling workbook with the bid tab, line items, qualifications and queries.
What happens when I pick the winner?
The package closes, the price goes into Master Pricing and the subcontract is created in procurement, with its scope, matrix, attendances, payment schedule and documents generated to go with it.

Level your next package on it.

Tell us about a package with returns in. We will compare them and draft the queries on a demo call.