Every programme update is checked and frozen. Events, notices and what moved completion build up as the job runs, and nothing in the record can be edited or deleted afterwards.

Book a demo
Construction AI·Larkspur House › Delay Record
Delay Record
Larkspur House · delay events · 2 Dec
Construction AI+ Event
Events
5
1 agreed, 1 submitted
Notices due
2
nearest in 4 days
Completion date
01 Mar
in the contract
Forecast
17 Mar
at the 30 Nov update
RefEventRaisedNoticeState
DE-001Reception bulkhead · CCI-00702 SepServed on timeAgreed
DE-002RFI #004 answered late22 SepServed on timeSubmitted
DE-003Asbestos found, riser 213 OctServed 2 days lateAssessed
DE-004Access restriction, loading bay24 Nov4 days leftAssessed
DE-005Late ceiling grid information01 Dec12 days leftOpen
The notice period comes from the contract. Entries are added to the record as they happen and cannot be edited or deleted afterwards.

The tools

From the planner’s file to the extension of time, in the order it happens.

Construction AI·Larkspur House › Programme
Programme
Project schedule and Gantt chart • 14 tasks
Construction AI
+Week ▾⚠ Critical PathBaselinesExport
WBSTask NameStart%
1PHASE 1: MOBILISATION01 Sep
1.1Possession and set-up01 Sep100%
2PHASE 2: STRIP OUT08 Sep
2.1Strip-out, levels 1–308 Sep0%
3PHASE 3: PLANT DECK15 Sep
3.1Plant deck steelwork15 Sep0%
3.2AHU lifts and installation13 Oct0%
4PHASE 4: FIT-OUT29 Sep
4.1Partitions and ceilings29 Sep0%
4.2Raised access floors27 Oct0%
4.3M&E first and second fix03 Nov0%
4.4Finishes and decorations14 Dec0%
5Commissioning and handover25 Jan0%
6Practical completion01 Mar
Sep 2026
Oct
Nov
Dec
Jan 2027
Feb
W36
W40
W44
W48
W52
W4
W8
PHASE 1: MOBILISATION
Possession and set-up
PHASE 2: STRIP OUT
Strip-out
PHASE 3: PLANT DECK
Plant deck steelwork
AHU lifts and installation
PHASE 4: FIT-OUT
Partitions and ceilings
Raised access floors
M&E first and second fix
Finishes and decorations
Commissioning and handover
01

Your planner’s file, on a real scheduling engine

Bring in the P6, Asta or MS Project file. Float and the critical path are recalculated after every save, and each update is kept as a lettered revision.

  • Baselines sit under the bars.
  • Revisions can be compared, restored or accepted as the baseline.
  • Activities are matched across re-imports, even when the planner has renumbered them.
Construction AI·Larkspur House › Delay Record › Update check
Update check
Larkspur House · revision D, status date 30 Nov · before it is frozen
1 to fixFreeze update
Hard findings
3
1 fixed, 1 accepted, 1 open
Notes
2
for the planner
Last frozen
Rev C
31 Oct, by S. Okafor
FindingWhereState
Actual start later than the status date4.2 Raised access floorTo fix
Finished, but duration still remaining3.1 Plant deck steelFixed
Logic removed since revision C4.3 to 4.4Accepted · S. Okafor
Open end, no successor5 CommissioningNote
Duration changed on the critical path4.1 PartitionsNote
Accepted with a reason
“Link 4.3 to 4.4 removed on purpose: first fix now runs level by level.” S. Okafor, 1 Dec
A hard finding is fixed, or accepted by a named person with a reason. Only then can the update be frozen.
02

Every update is checked before it is frozen

Before an update joins the record it is checked. A hard finding is fixed, or accepted by a named person with a reason.

  • The checks run by themselves on every import.
  • Loops, open ends and impossible dates are found before anyone relies on the update.
  • Once frozen, an update cannot be changed.
Construction AI·Larkspur House › Delay Record
Delay Record
Larkspur House · delay events · 2 Dec
Construction AI+ Event
Events
5
1 agreed, 1 submitted
Notices due
2
nearest in 4 days
Completion date
01 Mar
in the contract
Forecast
17 Mar
at the 30 Nov update
RefEventRaisedNoticeState
DE-001Reception bulkhead · CCI-00702 SepServed on timeAgreed
DE-002RFI #004 answered late22 SepServed on timeSubmitted
DE-003Asbestos found, riser 213 OctServed 2 days lateAssessed
DE-004Access restriction, loading bay24 Nov4 days leftAssessed
DE-005Late ceiling grid information01 Dec12 days leftOpen
The notice period comes from the contract. Entries are added to the record as they happen and cannot be edited or deleted afterwards.
03

Each event, from open to agreed

A delay event is raised when it happens and moves from open to assessed, submitted and agreed. The assistant can assess an event and re-run the analysis the way the other side’s expert might.

  • An event points at the instruction, RFI or diary entry behind it.
  • Mitigation options are previewed on the programme before you choose one.
  • Entries are added as they happen and cannot be edited or deleted afterwards.
Construction AI·Larkspur House › Delay Record › Notices
Notices
Larkspur House · periods taken from the contract’s key terms · 2 Dec
2 to serve
Served
4
3 on time
Late
1
N-004, by 2 days
To serve
2
nearest 6 Dec
RefNoticeEventDueServedState
N-001Notice of delayDE-00116 Sep04 SepOn time
N-002Further particularsDE-00130 Sep28 SepOn time
N-003Notice of delayDE-00206 Oct24 SepOn time
N-004Notice of delayDE-00327 Oct29 Oct2 days late
N-005Notice of delayDE-00406 Dec—4 days left
N-006Notice of delayDE-00514 Dec—12 days left
A late notice is shown as late. The days left are counted from the contract, not from memory.
04

The notice the contract requires, with the days left

The notice periods come from the contract. Each event shows whether its notice went on time, went late or is still to serve.

  • The days left are counted for you.
  • A late notice is shown as late, not hidden.
  • One register for every notice on the job.
Construction AI·Larkspur House › Delay Record › Windows
Windows
Larkspur House · what moved completion at each update
Construction AIEOT submission
Win.UpdateCompletionMovedDriven by
W101 Sep01 Mar—Baseline accepted
W230 Sep04 Mar+3 dDE-001 reception bulkhead
W331 Oct09 Mar+3 dDE-002 RFI #004 answered late
W430 Nov17 Mar+6 dDE-003 asbestos, riser 2
Completion, update by update01 Mar to 17 Mar
W1
W2
W3
W4
Worked out from the record by rule. Every judgement in the submission is written and signed by a person.
05

What moved completion, update by update

At each status date the record shows what drove completion, what slipped and what was added or removed. The engine gives its own forecast beside the planner’s date.

  • Worked out from the record by rule, not written by the AI.
  • Float gained and lost in each window.
  • A cumulative as-built programme shows how much of it the evidence covers.
Construction AI·Larkspur House › Delay Record › EOT submission
Extension of time · submission 1
Larkspur House · event DE-001 · draft
2 sections to writeExport
From the recordSource
Instruction CCI-007 confirmed on 2 Sep: bulkhead added to reception.DE-001
Notice of delay served on 4 Sep, within the period.N-001
Completion moved from 1 Mar to 4 Mar at the 30 Sep update.W2
Your caseWritten and signed by a person
Cause and entitlementSigned · S. Okafor
Concurrent delayTo write
Mitigation takenTo write
Cause and entitlement · signed
“The bulkhead was instructed after the ceiling package was let. It is a change to the works, and the delay to completion follows from it.” S. Okafor, 1 Oct
The facts are placed from the record. The argument is yours: nothing in a judgement section is written for you.
06

The extension of time, with the facts already in it

The submission takes its facts from the record. Cause, entitlement and mitigation are yours to write, and every judgement is signed by a person.

  • Each fact arrives with the event, notice or window it came from.
  • Nothing in it is the model’s opinion.
  • It goes out as a document you can send.

Works with the rest

Nothing on this page is typed a second time somewhere else.

Questions

Which programme files does it read?
Primavera P6 (.xer), Asta Powerproject (.pp) and MS Project (.mpp and XML). Programmes go back out as P6 or MS Project files, Excel and PDF.
Can the record be edited?
No. Entries are added as they happen. Nothing in the record can be edited or deleted afterwards.
Does the AI decide what caused a delay?
No. What moved completion in each window is worked out from the record by rule. The assistant can assess an event and test the analysis, and a person writes and signs every judgement.
Where do the notice periods come from?
From your contract. The main contract is read whichever form it is on: JCT, NEC4, FIDIC or bespoke.

Bring a programme.

Send us a P6, Asta or MS Project file. We will open it on a demo call and show you what it is telling you.