Contemporaneous Records: The Delay Evidence That Wins Extension of Time Claims

Delay claims are won on records made at the time, not on recollections a year later. Here's which records carry weight, how emails and programme updates should be kept, what notices you can't afford to miss, and how to build the record as you go.

SMStephen Mckenna MCIOB
7 minutes read

Contemporaneous Records: The Delay Evidence That Wins Extension of Time Claims

Every delay dispute I've seen comes down to the same question: what can you prove happened, and when?

Not what you remember. Not what everyone on site knew. What's written down, dated, and made at the time by someone who was there. Records like that are called contemporaneous records, and they decide more extension of time claims than any expert's method or barrister's argument.

The frustrating part is that the records that win claims cost almost nothing to keep at the time, and are impossible to create afterwards. Here's what they are and how to keep them so they hold up.

Why records made at the time win

Memory is a poor witness. People remember the version of events that suits them, and they honestly believe it. Once a dispute starts, everyone's recollection drifts towards their own side.

The courts know this. In Gestmin v Credit Suisse (2013), the judge said that the best approach in a commercial case is to place little if any reliance on witnesses' recollections, and to base findings of fact on the documents and on known or probable facts. That approach has been followed many times since, including in construction disputes.

The Society of Construction Law's Delay and Disruption Protocol (2nd edition, 2017) makes the same point from the other direction. Its very first core principle is about programmes and records: the parties should keep good records during the project, so that delay can be worked out when it happens rather than argued about afterwards.

So the job is simple to state. Record what happened, on the day, in a form nobody can later say was written to suit the claim.

The records that carry weight

Programme updates

The programme is the backbone of any delay analysis, and most contractors weaken it without meaning to.

  • Keep every issued update, as issued. Each one shows what was planned and what was critical at that moment. If you update one file in place every month, you've overwritten your own evidence.
  • Record the status date. Every update needs a clear data date. Without it, nobody can say what the update reflected.
  • Record actual dates as they happen. Actual starts and finishes entered at the time are evidence. Actual dates pieced together a year later from memory are not.
  • Don't change the logic quietly. If you re-sequence, record what changed and why. Unexplained logic changes between updates are the first thing the other side's expert will attack.

Our guide to delay analysis explains why a credible baseline and honest updates are the two things you can't analyse without.

The site diary

A site diary filled in every day is the closest thing to a witness who can't be cross-examined. The entries that matter most in a delay claim are:

  • what work actually happened, and where;
  • who was on site, by trade and headcount;
  • what stopped or slowed work, in plain words: "no access to level 3, M&E coordination drawings not received";
  • weather, if it affected work;
  • instructions received on site, and from whom.

Write the cause, not just the effect. "Bricklayers stood down" is a fact. "Bricklayers stood down — window openings not confirmed, see RFI 042" is evidence.

Emails and letters

Emails are often the best record of when information was asked for, when it arrived and what was said about delay at the time. They're also the records contractors handle worst.

  • File them to the project. An email that only exists in a site manager's personal inbox is an email you'll lose when they leave.
  • Keep whole threads, with attachments. A forwarded, trimmed chain looks edited, because it is.
  • Never alter a record. Don't edit, re-date or "tidy up" anything you may rely on later.
  • Put formal things in formal letters. Delay notices, instructions and requests for information belong in the contract's required form, not buried in the fourth reply of a chat about something else.
  • Mind WhatsApp. Instructions given by text or messaging app are still instructions. Screenshot them with the date, file them, and confirm them in writing.

RFIs and information release

Late design information is one of the most common causes of delay. You can only prove it if you can show when you asked, when the reply was due, and when it actually came. Every RFI should have a date raised, a date required, and the date answered. A schedule of information required, agreed at the start, turns "it was late" into "it was 23 days late against the date you agreed".

Photos

Dated progress photos, taken from the same positions each week, show what was built and when. They're hard to argue with. Make sure the date is in the file, and that someone can tell where each photo was taken.

Minutes, instructions and notices

Progress meeting minutes, site instructions and the notices you gave under the contract complete the picture. Check minutes when they're issued and correct them in writing if they're wrong. Unchallenged minutes become the agreed record.

Notices: the record you can't afford to miss

The best records in the world won't help if the contract's notice requirements weren't met.

  • JCT contracts require notice of delay when it becomes reasonably apparent that progress is being, or is likely to be, delayed. In practice, that means straight away.
  • NEC4 is stricter. A contractor who doesn't notify a compensation event within eight weeks of becoming aware of it generally loses the entitlement, subject to the contract's exceptions. Early warnings matter too.
  • Bespoke amendments often tighten these further. Read your own contract's notice clauses at the start of the job, diarise them, and make sure the site team knows what triggers one.

Late notice turns a strong claim into an argument about whether you're entitled to claim at all. Our practical guide to extension of time claims covers notices and submissions in more detail.

Seven habits that build the record as you go

  1. Write the diary every day, before you leave site. Tomorrow's version of today is already less reliable.
  2. Issue the programme update on a fixed cycle, with a status date, and keep every version.
  3. Name the cause. Every delay entry should say why, and point to the RFI, instruction or email behind it.
  4. File emails to the project the day they're sent or received.
  5. Give notice early. A notice that turns out to be unnecessary costs nothing. A missed one can cost the claim.
  6. Correct wrong minutes in writing, within days.
  7. Never change a record after the event. If something needs correcting, add a dated correction and keep the original.

None of this is clever. It's discipline. The contractors who win delay claims aren't the ones with the best analysts; they're the ones whose site teams wrote things down.

How Construction AI handles it

At Construction AI, the Delay Record keeps the programme evidence for you. Each programme update is checked before it's frozen: hard problems have to be fixed, or accepted by a named person with a reason. Once frozen, an update can't be edited or deleted. Records are only ever added, and each one is chained to the one before, so any later change would show. A notices register applies your contract's notice periods and shows which notices were on time, which were late and how many days are left. Delay events move through a register from open to assessed, submitted and agreed. A windows analysis shows what moved completion in each period. And the extension of time submission is drafted in Word and PDF from the record's facts, with every judgement in it written by a person, not the software.

Alongside it, the site diary, RFIs and correspondence (each with its reply-due date) all live in the same project, so the evidence behind each delay event is a click away rather than a search through inboxes.

The time to build your delay evidence is before you know you'll need it. Records made on the day win. Records made afterwards get picked apart.

Frequently asked questions

What are contemporaneous records in construction?

Records made at the time events happened, by people who were there: site diaries, programme updates with their status dates, progress photos, emails and letters, meeting minutes, RFIs and their responses, delivery records, labour returns and the notices given under the contract. They carry far more weight in a delay dispute than witness statements written later, because they were made before anyone knew there would be a dispute.

Do emails count as evidence in a delay claim?

Yes. Emails are often the best evidence of when information was requested, when it arrived and what was said about delay at the time. They're only useful if you can find them, so file project emails to the project rather than leaving them in personal inboxes, keep whole threads with attachments, and never edit or forward-and-trim a record you may need later.

How long do I have to give notice of delay?

It depends on the contract. JCT contracts require notice when it becomes reasonably apparent that progress is being or is likely to be delayed — in practice, straight away. Under NEC4, a contractor who doesn't notify a compensation event within eight weeks of becoming aware of it generally loses the entitlement, subject to the contract's exceptions. Read your own contract's notice clauses at the start of the job and diarise them.

Why do courts prefer documents to witness evidence?

Because memory is unreliable and gets rewritten, especially once a dispute starts. English courts have said that the best approach is to place little reliance on recollection and to base findings on the documents and known facts. A record made on the day is evidence of what happened; a statement written a year later is evidence of what someone now believes happened.

What should I do with programme updates for delay evidence?

Keep every issued update as it was issued, with its status (data) date, and never overwrite one with the next. Record actual start and finish dates as they happen. A run of honest, consecutive updates is what lets an analyst show what was critical at each point and what moved completion; a single programme updated in place destroys that evidence.

SM

Stephen Mckenna MCIOB

30+ years in UK commercial construction, from site management to director level. Now building the project management tools he wished he'd had.

Stop losing money on problems you can see coming

Tier-one contractor processes shouldn't only be available to tier-one contractors. Drawing registers, document control, RFIs, programmes, financial tracking — built for how you actually run projects. One platform, every module, every user — priced to your business. Leave your email and we'll show you round.

By subscribing, you agree to our Privacy Policy.

Run the next job on it.

Tier-one processes for the whole business. One platform, every module, every user, priced to your business.