COSHH on Construction Sites: A Practical Guide for Contractors

Silica dust, cement, isocyanates, solvents, diesel fumes: construction is full of hazardous substances, and a filed safety data sheet isn't a COSHH assessment. Here's what the COSHH Regulations require, the substances that matter most on site, and how to keep a register that's actually used.

SMStephen Mckenna MCIOB
6 minutes read

COSHH on Construction Sites: A Practical Guide for Contractors

Ask most site teams about COSHH, and they'll point you to a folder of safety data sheets. Every product's in there. Some of the sheets are even current.

But a folder of data sheets isn't COSHH compliance. The regulations ask you to assess the risk of the work you're actually doing with those products, control it, and make sure the people doing it know. On construction sites, where some of the most harmful substances aren't bought products at all but dust created by the work itself, that difference matters.

What the COSHH Regulations require

The Control of Substances Hazardous to Health Regulations 2002 (as amended) require employers to:

  1. Assess the risks to health from hazardous substances their work creates or uses, and decide what precautions are needed.
  2. Prevent exposure, or where that isn't reasonably practicable, control it adequately.
  3. Make sure controls are used and maintained: extraction checked, RPE fit-tested and worn.
  4. Monitor exposure where needed.
  5. Provide health surveillance where needed, for example for workers exposed to substances that cause occupational asthma or dermatitis.
  6. Give workers information, instruction and training about the risks and the controls.
  7. Plan for accidents and emergencies, such as spills.

COSHH covers substances and dusts, fumes, vapours and mists hazardous to health. It doesn't cover asbestos or lead, which have their own regulations (the Control of Asbestos Regulations 2012 and the Control of Lead at Work Regulations 2002), though the approach is similar.

The substances that matter most on site

SubstanceWhere it comes fromMain health risk
Respirable crystalline silicaCutting, drilling, grinding, chasing concrete, brick, block, stone and tilesSilicosis, lung cancer, COPD
Wood dustCutting and sanding timber and board, especially hardwood and MDFAsthma, nasal cancer
Cement and wet concreteMixing, placing, screeding, renderingDermatitis, chemical burns
IsocyanatesSome spray paints, foams, sealants and coatingsOccupational asthma
SolventsAdhesives, paints, coatings, cleanersDizziness, dermatitis, organ damage
Diesel engine exhaustPlant and generators, especially in enclosed spacesLung disease and cancer
Lead (separate regulations)Removing old paintwork, roofing workLead poisoning

The biggest point to notice is that the most serious hazard, silica, isn't on any delivery note. It's created by the work. The UK workplace exposure limit for respirable crystalline silica is 0.1 mg/m³, averaged over 8 hours, and cutting or grinding without controls can exceed it within minutes. That's why water suppression, on-tool extraction and suitable RPE are the expected controls, and why "dry cutting" should never appear in a method statement.

A COSHH assessment, step by step

  1. Identify the substances. Bought products (from their labels and safety data sheets) and substances the work creates (dust, fume).
  2. Identify who's exposed, how and how much. Breathing it in, skin contact, swallowing, eyes. The operative doing the task, and others nearby.
  3. Decide the controls, in this order:
    • eliminate or substitute (a water-based product instead of a solvent one; pre-cut materials off site);
    • engineering controls (water suppression, on-tool extraction, ventilation);
    • procedures (limit the time, keep others away, good housekeeping);
    • PPE and RPE as the last line, properly selected and fit-tested.
  4. Record it, with the significant findings.
  5. Put it in the RAMS for the task, so the controls reach the workface.
  6. Brief it. Through the RAMS briefing and toolbox talks.
  7. Check it's working, and review it when the product, task or site changes.

Safety data sheets: essential, not sufficient

A safety data sheet (SDS) is the supplier's information about a product: its hazards, its hazard statements (H-codes, such as H317 "may cause an allergic skin reaction"), safe handling, storage, PPE, first aid and disposal. Suppliers must provide one for hazardous products.

It's an essential input to your assessment, but it's written about the product in general, not about your task on your site. Use it to build your assessment; don't treat it as the assessment. And keep it current: suppliers revise them.

A register that's actually used

A COSHH register earns its keep when it's the place site teams go before they start a task, not a folder audited once a year. For every hazardous product used, it should hold:

  • the product, supplier and the current safety data sheet;
  • its hazard statements and the health risks, by route of exposure;
  • the controls and PPE required;
  • storage, handling and disposal;
  • first aid and spill action;
  • a review date;
  • the link to the COSHH assessment and the RAMS that use it.

Keep it company-wide, so the assessment for a sealant you use on every job is written once and reused, then add project-specific products as they arrive. Our guide to what CDM 2015 actually requires of RAMS covers how the assessment flows into the method statement, and our guide to toolbox talks covers getting it to the workforce.

How Construction AI handles it

At Construction AI, the COSHH register is company-wide: each product holds its supplier, hazards, health risks and exposure routes, storage, handling and disposal, PPE, spill action and first aid, review dates and the safety data sheet itself. The register, along with the company's PPE and hazard libraries, feeds the RAMS wizard directly, and the AI generates COSHH and PPE content for the method statement from the task, so the controls in the register are the controls in the RAMS.

COSHH on site isn't about the folder. It's about the dust from the next cut, the cement on the next pair of hands, and whether the person doing the work knows what's in place to protect them.

Frequently asked questions

What does COSHH require on a construction site?

The Control of Substances Hazardous to Health Regulations 2002 require employers to assess the risks from hazardous substances their work creates or uses, prevent exposure or, where that isn't reasonably practicable, control it adequately, make sure controls are used and maintained, monitor exposure and provide health surveillance where needed, and give workers information, instruction and training. On site, that means a COSHH assessment for each substance and task, controls in the RAMS, and workers briefed on both.

Is a safety data sheet a COSHH assessment?

No. A safety data sheet (SDS) is the supplier's information about a product's hazards and how to handle it. A COSHH assessment is your assessment of the risk from using that product in your task, on your site, and the controls you'll use. The SDS is an essential input to the assessment, but filing it doesn't meet the duty to assess.

What are the most common hazardous substances in construction?

Respirable crystalline silica from cutting, drilling and grinding concrete, brick and stone; wood dust; cement and wet concrete, which cause dermatitis and burns; isocyanates in some paints, foams and sealants; solvents in adhesives and coatings; and diesel engine exhaust. Asbestos and lead are covered by their own regulations rather than COSHH.

What is the workplace exposure limit for silica?

The UK workplace exposure limit for respirable crystalline silica is 0.1 mg/m³, averaged over 8 hours. In practice, construction tasks that cut or grind silica-containing materials can exceed that quickly, so controls such as water suppression or on-tool extraction, together with suitable respiratory protective equipment, are expected.

What should a COSHH register contain?

Every hazardous product used, with its supplier and current safety data sheet, its hazard statements, the health risks and routes of exposure, the controls and PPE required, storage, handling and disposal, first aid and spill action, and a review date. It should link to the COSHH assessments and the RAMS for the tasks that use each product.

SM

Stephen Mckenna MCIOB

30+ years in UK commercial construction, from site management to director level. Now building the project management tools he wished he'd had.

Stop losing money on problems you can see coming

Tier-one contractor processes shouldn't only be available to tier-one contractors. Drawing registers, document control, RFIs, programmes, financial tracking — built for how you actually run projects. One platform, every module, every user — priced to your business. Leave your email and we'll show you round.

By subscribing, you agree to our Privacy Policy.

Run the next job on it.

Tier-one processes for the whole business. One platform, every module, every user, priced to your business.