Non-Conformance Reports (NCRs) in Construction: Raising, Responding and Closing Them Properly

An NCR that just says 'not to spec' gets a shrug and a patch. One that's raised properly gets the work fixed and stops it happening again. Here's what a non-conformance is, what an NCR must contain, the decisions you can make, and how to close one out.

SMStephen Mckenna MCIOB
6 minutes read

Non-Conformance Reports (NCRs) in Construction: Raising, Responding and Closing Them Properly

Every site has non-conforming work. Fire-stopping that isn't the tested system. Insulation with gaps. A screed that's out of tolerance. Fixings at the wrong centres. The question isn't whether it happens; it's what you do when you find it.

On a lot of sites, the answer is a quick word with the foreman, a patch, and a note in someone's book. Sometimes that's enough. Often it isn't: the same problem turns up on the next floor, nobody can show what was done about it, and at handover the client's inspector finds the lot.

A non-conformance report (NCR) is the formal way to deal with work that doesn't meet the requirement. Done properly, it gets the work fixed, finds out why it happened, and stops it happening again. Here's how.

What counts as a non-conformance

A non-conformance is work, materials or a process that doesn't meet a specified requirement. The requirement might be:

  • the drawings or the specification;
  • a British Standard or the manufacturer's installation instructions;
  • an approved submittal, sample or mock-up;
  • the building regulations, or a tested system's conditions (fire-stopping and cladding are the classic cases);
  • your own quality procedures, or an inspection and test plan hold point.

If it fails a requirement, it's a non-conformance. If you can't name the requirement it fails, it may be a preference, not a non-conformance, and an NCR is the wrong tool.

NCR or snag?

  • A snag is usually a minor, visible defect in finished work: a scuffed door, a missing cover plate, paint on glass. It's fixed in the normal course of completion. Our guide to defects and snag lists covers those.
  • An NCR is for work that fails a requirement, often hidden or structural, where the fix needs a decision, the cause needs investigating, and you need a formal record. Fire-stopping, structural fixings, waterproofing, cladding.

A snag that keeps coming back is telling you something. Raise an NCR.

What a good NCR contains

  1. A unique number and the date.
  2. The location and extent. Not "level 3" but "level 3, gridlines C–E / 4–7, all riser penetrations". If you don't know the extent yet, say so and make finding it an action.
  3. What was found, in plain words, with photos.
  4. The requirement it fails. The drawing number and revision, the specification clause, the standard, or the system's test evidence. This is what turns an opinion into a non-conformance.
  5. Who raised it and who is responsible.
  6. Immediate action. Is following work on hold? Do the ceilings stay off until it's fixed? Is material quarantined?
  7. Disposition. What will be done (see below), and who decided.
  8. Root cause. Why it happened.
  9. Corrective and preventive action. What fixes this one, and what stops the next.
  10. Verification and close-out. Who checked the fix, when, with what evidence.

The most common weakness is item 4. An NCR that says "poor workmanship" without citing the requirement invites the response "it's fine". One that says "fails specification clause K10/290: boards to be fixed at 300 mm centres; measured at 450–600 mm, see photos 1–6" doesn't.

The decisions: disposition

When work doesn't conform, there are four usual options:

DispositionMeansWho should agree
ReworkTake it out or redo it so it conformsYou
RepairFix it to an approved method that restores the requirementYou, and the designer if the method differs from the original
Accept as is (concession)Leave it, because it still meets the purposeThe designer, and the client where the contract requires
Reject and replaceRemove non-conforming materials or products entirelyYou

A concession is a design decision, not a commercial one. Don't accept non-conforming work because fixing it is expensive without the designer's written agreement that it's acceptable.

Root cause, corrective and preventive action

The difference between a site that has the same NCR twelve times and one that has it once is root cause analysis. Ask "why?" until you reach something you can change:

  • The fixings are at the wrong centres. Why? The operatives didn't know the specified centres. Why? The drawing on site was the previous revision. Why? The subcontractor's supervisor printed a set at the start and never updated it.

The corrective action fixes this case: refix level 3. The preventive action stops it recurring: supervisors work from the current drawing register, and the hold point inspection checks centres before boarding. "Operative error, retrained" is almost never the real root cause.

Closing out

An NCR isn't closed when the subcontractor says it's fixed. It's closed when someone has checked that it's fixed, against the same requirement, and recorded the evidence: a photo, a re-inspection, a test result. Then:

  • Keep the record with the project's quality records and the O&M information where relevant. On higher-risk buildings it's part of the golden thread.
  • Recover the cost where the contract allows. A non-conformance that caused you cost can support a contra charge, provided you follow the notice rules.
  • Look for trends. Several NCRs on one trade, one element or one cause is a pattern. Raise it at the next progress meeting.

How it fits with inspections

Most NCRs are found at inspections: hold points on the inspection and test plan, pre-close-up inspections before ceilings go on, and pre-handover walks. The better your inspections, the earlier you find non-conformances, and the cheaper they are to fix. Fire-stopping found before the ceiling goes on is an hour's work. Found after, it's a ceiling.

At Construction AI, inspections and tests are recorded on site with attendees and pass/fail items with notes and photos, and the completed inspection can be emailed as a PDF, so the evidence for an NCR, and for closing it, is captured where the work is.

Non-conforming work is inevitable. Non-conforming work that nobody recorded, nobody understood and that turns up again on the next floor isn't. Cite the requirement, find the cause, check the fix.

Frequently asked questions

What is a non-conformance report in construction?

A non-conformance report (NCR) is a formal record that work, materials or a process don't meet the specified requirements — the drawings, the specification, a standard or an approved submittal. It records what's wrong and where, who is responsible, what will be done about it, why it happened and what will stop it happening again, and it stays open until the fix has been checked.

What is the difference between an NCR and a snag?

A snag is usually a minor, visible defect in finished work — a scuffed door, a missing cover plate — fixed in the normal course of completion. An NCR is for work or materials that don't meet the specified requirement, often hidden or structural, where the fix needs a decision, the cause needs investigating, and the outcome needs a formal record. A repeated snag can become an NCR.

What should an NCR include?

A unique number and date; the location and extent; what was found, with photos; the requirement it fails, citing the drawing, specification clause or standard; who raised it and who is responsible; any immediate action such as a hold on following work; the proposed disposition; the root cause; corrective and preventive actions; and the verification and sign-off that closed it.

What are the options for dealing with a non-conformance?

The usual dispositions are to rework it so it conforms, repair it to an approved method, accept it as it is (a concession) with the designer's and, where needed, the client's agreement, or reject and replace it. Whichever is chosen, record who decided, on what basis, and any effect on cost or programme.

What is the difference between corrective and preventive action?

Corrective action fixes the cause of the non-conformance that has happened, so this problem is dealt with properly. Preventive action stops the same cause producing the same problem elsewhere — on the next floor, the next package or the next project. A good NCR response includes both, based on a real root cause, not just "operative error".

SM

Stephen Mckenna MCIOB

30+ years in UK commercial construction, from site management to director level. Now building the project management tools he wished he'd had.

Stop losing money on problems you can see coming

Tier-one contractor processes shouldn't only be available to tier-one contractors. Drawing registers, document control, RFIs, programmes, financial tracking — built for how you actually run projects. One platform, every module, every user — priced to your business. Leave your email and we'll show you round.