The Three-Way Match: Stop Paying for Materials You Never Received

Matching the order, the delivery and the invoice is basic purchasing control — and most contractors don't do it. Here's how the three-way match works on a construction site, where it breaks, and how to fix it.

SMStephen Mckenna MCIOB
7 minutes read

The Three-Way Match: Stop Paying for Materials You Never Received

Ask a contractor's accounts team how they check a materials invoice and you'll usually hear some version of: "We send it to the site manager to approve." The site manager, who's looking at it six weeks after the lorry left, signs it because it looks about right. It gets paid.

Nobody checked whether the quantity on the invoice matches what was actually tipped on site. Nobody checked whether the price matches what the buyer agreed. And nobody notices that the 40 lengths of 100mm pipe on the invoice were 32 on the docket, because the docket is in a site cabin drawer or a van footwell.

That's not fraud — most suppliers aren't trying it on. It's drift. Short deliveries that never get credited, price increases that slip through, duplicate invoices for the same drop, materials delivered to the wrong job and charged to yours. On a busy project it adds up to real money, and it all comes off your margin.

The fix is old and boring and works: the three-way match.

What the three-way match is

Before you pay a supplier, three documents have to agree:

  1. The order — what you agreed to buy, how much, and at what price. Whatever you call it (purchase order, call-off, supply agreement), it's the commitment.
  2. The delivery record — what actually arrived on site, counted and recorded by someone who saw it. The supplier's delivery note or docket is evidence; your own record of what you counted is the control.
  3. The invoice — what the supplier is charging.

If the order, the delivery and the invoice agree on item, quantity and price, the invoice is paid. If they don't, it's held and the difference is sorted out first. That's the whole idea. A two-way match (order to invoice) catches price drift but not short deliveries. A three-way match catches both.

Why construction makes it hard

In a warehouse, goods-in and accounts are a corridor apart. On a construction project they can be a hundred miles apart and weeks out of step. The things that break the match are specific to our industry:

  • Deliveries happen where accounts can't see them. The person who counts the delivery is a site manager or a storeman with a lorry waiting. If recording it takes more than a minute, it doesn't happen.
  • Part deliveries and call-offs. One order for 2,000 blocks, delivered in six drops over three months, invoiced in four invoices that don't line up with any of the drops.
  • Substitutions. The supplier sends an equivalent product, or a different pack size, and the invoice describes it differently from the order.
  • Price changes. The quote was held for 30 days; the call-off happened on day 45.
  • No order at all. Somebody on site rang the merchant direct. The first anyone in the office knows about it is the invoice.
  • Hire, fees and services. There's no delivery note for a week's hire of a telehandler or a consultant's fee. These still need checking, but not by waiting for a delivery that will never be booked in.
  • Invoices for other jobs. Same supplier, two projects, one account — and the materials for the other job get charged to yours.

How to make it work on site

1. Every purchase starts with an order

No order, no payment. That rule only works if raising an order is easy and fast, and if the order sits against a budget — so the buyer can see what's committed against the cost code before they commit more. If your ordering process is a phone call and a scribbled note, the three-way match has nothing to match against.

2. Make recording a delivery a one-minute job

This is where most systems fail. If the site manager has to type out the delivery, they won't — not with a driver waiting and a crane booked. The record needs to start from the order: the expected lines and quantities are already there, and they confirm what arrived. A full, correct drop should be one tap. A short or over delivery should be obvious as they type.

What to capture at the lorry:

  • Which order it's against.
  • What arrived, line by line, including anything short, damaged or refused.
  • A photo of the supplier's docket.
  • Who received it, and when.

Keep prices off the site screen. The person counting doesn't need them, and showing them invites "near enough" judgements.

3. Match the invoice to both

When the invoice arrives, it's checked against the order (price and item) and the delivery record (quantity). Set a sensible tolerance for pennies and rounding, but anything outside it is held, not paid "subject to". Common outcomes:

  • Short delivery: hold the invoice until a credit note arrives or the balance is delivered.
  • Over delivery: decide whether to keep and accept the extra (and the cost) or return it.
  • Price higher than the order: go back to the buyer, not the site manager. Either the price was agreed and the order is amended, or the supplier issues a credit.
  • Item doesn't match: confirm whether it's a substitution site accepted, or a mistake.
  • Duplicate invoice: catch it by invoice number and amount before it's paid twice.

4. Treat hire and services differently

Hire and services skip the delivery leg. Match them order to invoice, with confirmation from site that the plant was on hire for the period charged — especially the off-hire date, which is where hire bills quietly grow.

5. Accrue what's been delivered but not invoiced

A delivery record is cost the moment it's booked in, even if the invoice is weeks away. If you only post cost when invoices arrive, your cost-value reconciliation will flatter the job every month until the invoices catch up. The delivery record gives you a draft cost you can accrue, which the invoice then settles rather than duplicates.

A word on VAT and CIS

The three-way match is about quantity and price, but invoices also carry tax treatment, and that's worth checking at the same point. The domestic reverse charge applies to construction services, not to a straight supply of materials, so a supply-and-fix invoice and a materials-only invoice from the same supplier can need different VAT treatment. CIS applies to the labour part of a subcontractor's invoice, not to materials. If your matching step is where invoices get looked at properly, it's also where these get caught.

What good looks like

You'll know the three-way match is working when:

  • Nothing is bought without an order against a budget.
  • Every delivery is recorded on the day, against its order, by the person who saw it.
  • Invoices that agree are paid without anyone chasing approvals.
  • Invoices that don't agree are held automatically, with the reason visible.
  • Your CVR includes delivered-not-invoiced cost every month.

It's not glamorous. But on a job with a few hundred deliveries, it's the difference between knowing your material cost and hoping.

How Construction AI handles it

At Construction AI, orders to suppliers are raised as supply agreements in Procurement, and each one draws on a committed budget for its cost code, so you can't order past what's been committed. Site books deliveries in on a phone, starting from the order's outstanding quantities, so All present and correct records a full drop in one tap and short or over deliveries show as you type — with no prices on the site screen. Booking in raises a draft cost against the order. When the supplier's invoice arrives, it's matched to the order and the delivery, settles the draft cost rather than duplicating it, and an invoice that disagrees with what was ordered or delivered is stopped before it's paid. Hire and fees, which have no delivery, still go through on the order. The match runs in the background; people only look at the invoices that don't agree.

The three-way match won't stop every dispute with a supplier. But it means the disputes happen before you've paid, not after.

Frequently asked questions

What is a three-way match?

A three-way match checks three documents against each other before a supplier invoice is paid: the order (what you agreed to buy, at what price), the delivery record (what actually arrived on site) and the invoice (what the supplier is charging). If all three agree, the invoice is paid. If they don't, the difference is resolved before any money goes out.

Why is the three-way match hard in construction?

Because deliveries happen on site and invoices arrive at the office, usually weeks apart, with the delivery note in between — often in a van footwell. Part deliveries, call-off orders, price changes, substitutions and hire charges with no physical delivery all make matching harder than in a warehouse.

What should happen when a delivery is short?

Record what actually arrived at the time of delivery, against the order line, and get the driver's docket marked. The invoice should then be held until a credit note or the balance arrives. Paying the full invoice and chasing the shortfall later almost never recovers the money.

Do hire charges and services need a delivery record?

Not in the same way. Plant hire, fees and services have no delivery note, so the middle leg of the match is the hire record or confirmation that the service was provided. These should be matched order-to-invoice with a check from site, rather than held waiting for a delivery that will never be booked in.

How does the three-way match help CVR?

Deliveries booked in on site but not yet invoiced are real cost. If you only record cost when the invoice arrives, your cost-value reconciliation understates cost and overstates margin. A delivery record lets you accrue that cost in the month it was incurred.

SM

Stephen Mckenna MCIOB

30+ years in UK commercial construction, from site management to director level. Now building the project management tools he wished he'd had.

Stop losing money on problems you can see coming

Tier-one contractor processes shouldn't only be available to tier-one contractors. Drawing registers, document control, RFIs, programmes, financial tracking — built for how you actually run projects. One platform, every module, every user — priced to your business. Leave your email and we'll show you round.

By subscribing, you agree to our Privacy Policy.

Run the next job on it.

Tier-one processes for the whole business. One platform, every module, every user, priced to your business.