TIDPs and the MIDP: Information Delivery Plans Explained for Contractors

Under ISO 19650 every task team plans what information it will deliver and when, and the main contractor rolls those plans into the MIDP. Here's what goes in a TIDP, how the MIDP is built, and how to stop it becoming a spreadsheet nobody updates.

SMStephen Mckenna MCIOB
6 minutes read

TIDPs and the MIDP: Information Delivery Plans Explained for Contractors

Ask most site teams when the M&E coordinated drawings for level 3 are due and you'll get a shrug, an email search, or "they said end of the month". Ask who's late on design information and you'll get opinions rather than a list.

ISO 19650 has an answer for this, and it's not complicated: every firm producing information plans what it'll deliver and when, and the main contractor rolls those plans into one master plan. The firm-level plan is the TIDP (task information delivery plan). The master plan is the MIDP (master information delivery plan).

On most projects these exist as spreadsheets. On most projects they're out of date by week three. Here's what they're meant to be, and how to keep them useful.

Where they fit in ISO 19650

If you're new to the standard, start with our plain-English guide to ISO 19650 for contractors. In short:

  • The client (the appointing party) sets out what information it needs.
  • The main contractor (the lead appointed party) agrees how its delivery team will meet that, and sets out who produces what in a responsibility matrix.
  • Each task team — each consultant or design-and-build subcontractor — plans its own deliverables in a TIDP.
  • The main contractor aggregates the TIDPs into the MIDP, checks they fit together, and manages delivery against it.

Each TIDP forms part of its task team's appointment, and the MIDP forms part of the main contractor's. They're not optional extras; they're part of the contract.

What goes in a TIDP

A TIDP lists the information a task team will produce. For each item — each information container, which might be a drawing, a model, a schedule or a report — it should show:

  • The container's name and title. Ideally the planned document number under the project's naming standard.
  • The author. Who in the task team is producing it.
  • The level of information need. How much detail it must contain for its purpose. The current standard for this is ISO 7817-1:2024 (it replaced EN 17412-1).
  • Dependencies. What it needs from other teams first — you can't size the ductwork until the structural openings are fixed.
  • Production time. How long it will take.
  • Delivery milestones. When it will be shared for comment, and when it will be published.

There's no compulsory template. A spreadsheet, a programme or a dedicated tool all work. Some teams list individual files; others list information production tasks, which changes less often. What matters is that it's specific enough to chase.

How the MIDP is built

The main contractor collects every TIDP and combines them into the MIDP. That's not just pasting spreadsheets together. Building the MIDP means:

  • Checking it against the responsibility matrix. Is everything the matrix says will be produced actually in someone's TIDP? Gaps here are design that nobody is doing.
  • Lining up dependencies across firms. If the M&E designer needs the architect's general arrangements by week 6 and the architect's TIDP says week 9, you've found a delay before it happens.
  • Allowing for review periods. Your own checking and the client's review take time. Build them in, or every "on time" delivery will be late for construction.
  • Baselining it. Fix the planned dates as a baseline, so slippage is visible later.
  • Recording the risks. Where delivery looks tight, note it and tell the client.

Keeping it alive

The MIDP's value is entirely in being current. The usual failure isn't that it was never written; it's that it was written once, for the BEP, and never touched again. A few habits keep it useful:

  1. Baseline once, forecast always. The baseline dates stay fixed. The forecast and actual dates change. If you overwrite the baseline every time a date moves, you can never show slippage.
  2. Match deliverables to real documents. When a document arrives in the CDE, it should tick off its line in the plan. If someone has to update the spreadsheet by hand, they won't.
  3. Let the plan tell you what's late. "Late", "due this week" and "at risk" should be worked out from the dates, not judged by eye in a meeting.
  4. Chase by firm. A list of late items grouped by firm, sent to each firm, is more useful than a 600-line register shared with everyone.
  5. Accept the firm's own format. Each consultant already has its own TIDP spreadsheet, often with columns grouped by RIBA stage. Forcing everyone onto your template is how you end up with two plans that disagree.
  6. Issue document numbers from the plan. If a firm needs a number for a new document, issuing it from the plan keeps the register, the plan and the naming standard in step.
  7. Review it when scope changes. A variation that adds a plant room adds drawings. Update the TIDPs and the MIDP with it.

Why contractors should care

It's tempting to see the MIDP as paperwork for the client's information manager. It isn't. It's the design programme. Late design information is one of the most common causes of delay on site, and the MIDP is where you'll see it coming — weeks before the trade turns up to find no construction drawings. It's also your evidence. When you're arguing about who caused a delay, a baselined MIDP showing when information was planned, forecast and actually delivered is worth more than any number of emails. Our guide to delay analysis covers why contemporaneous records like this matter.

How Construction AI handles it

At Construction AI, Document Control includes Deliverables: the information delivery plan for the project, with planned documents per firm, owners and milestones, against a baseline kept as insert-only history so slippage is always visible. You can import a firm's own TIDP spreadsheet — RIBA-stage column groups and merged cells included — rather than retyping it. Each deliverable is matched to the real document when it's uploaded, and late, due, at-risk, slipped and issued are worked out automatically. A chase list groups late items by firm and exports to Excel, and dashboards show delivery against the plan for every firm.

A TIDP is just a firm's promise about what it'll deliver and when. The MIDP is the main contractor keeping score. Keep the baseline fixed, let the documents tick themselves off, and chase by firm — and the plan becomes the early warning it was meant to be.

Frequently asked questions

What is a TIDP?

A task information delivery plan (TIDP) is a task team's plan of the information it will produce for a project: each information container, who authors it, its level of information need, its dependencies, how long it will take, and when it will be delivered at each milestone. Every task team — each consultant or design-and-build subcontractor — prepares one.

What is the MIDP?

The master information delivery plan (MIDP) is the lead appointed party's combined plan, built by aggregating every task team's TIDP and checking the dependencies between them and the review periods needed by the main contractor and the client. On most projects the main contractor prepares and maintains it.

Who is responsible for the MIDP?

The lead appointed party — usually the main contractor once appointed. It aggregates the TIDPs, baselines the deliverables and dates, tells task teams about changes, and records risks to delivery. The MIDP forms part of the lead appointed party's appointment, and each TIDP forms part of its task team's appointment.

What is level of information need?

Level of information need defines how much information a deliverable must contain for its purpose — its geometry, its alphanumerical data and its documentation. The current standard for it is ISO 7817-1:2024, which replaced EN 17412-1.

How often should the MIDP be updated?

Whenever scope or dates change, and at least as often as you report progress. The baseline should stay fixed so you can see slippage; the current forecast and actual delivery dates are what change. An MIDP that's only updated for the monthly report is a record of the past, not a plan.

SM

Stephen Mckenna MCIOB

30+ years in UK commercial construction, from site management to director level. Now building the project management tools he wished he'd had.

Stop losing money on problems you can see coming

Tier-one contractor processes shouldn't only be available to tier-one contractors. Drawing registers, document control, RFIs, programmes, financial tracking — built for how you actually run projects. One platform, every module, every user — priced to your business. Leave your email and we'll show you round.

By subscribing, you agree to our Privacy Policy.

Run the next job on it.

Tier-one processes for the whole business. One platform, every module, every user, priced to your business.