Under ISO 19650 every task team plans what information it will deliver and when, and the main contractor rolls those plans into the MIDP. Here's what goes in a TIDP, how the MIDP is built, and how to stop it becoming a spreadsheet nobody updates.
Ask most site teams when the M&E coordinated drawings for level 3 are due and you'll get a shrug, an email search, or "they said end of the month". Ask who's late on design information and you'll get opinions rather than a list.
ISO 19650 has an answer for this, and it's not complicated: every firm producing information plans what it'll deliver and when, and the main contractor rolls those plans into one master plan. The firm-level plan is the TIDP (task information delivery plan). The master plan is the MIDP (master information delivery plan).
On most projects these exist as spreadsheets. On most projects they're out of date by week three. Here's what they're meant to be, and how to keep them useful.
If you're new to the standard, start with our plain-English guide to ISO 19650 for contractors. In short:
Each TIDP forms part of its task team's appointment, and the MIDP forms part of the main contractor's. They're not optional extras; they're part of the contract.
A TIDP lists the information a task team will produce. For each item — each information container, which might be a drawing, a model, a schedule or a report — it should show:
There's no compulsory template. A spreadsheet, a programme or a dedicated tool all work. Some teams list individual files; others list information production tasks, which changes less often. What matters is that it's specific enough to chase.
The main contractor collects every TIDP and combines them into the MIDP. That's not just pasting spreadsheets together. Building the MIDP means:
The MIDP's value is entirely in being current. The usual failure isn't that it was never written; it's that it was written once, for the BEP, and never touched again. A few habits keep it useful:
It's tempting to see the MIDP as paperwork for the client's information manager. It isn't. It's the design programme. Late design information is one of the most common causes of delay on site, and the MIDP is where you'll see it coming — weeks before the trade turns up to find no construction drawings. It's also your evidence. When you're arguing about who caused a delay, a baselined MIDP showing when information was planned, forecast and actually delivered is worth more than any number of emails. Our guide to delay analysis covers why contemporaneous records like this matter.
At Construction AI, Document Control includes Deliverables: the information delivery plan for the project, with planned documents per firm, owners and milestones, against a baseline kept as insert-only history so slippage is always visible. You can import a firm's own TIDP spreadsheet — RIBA-stage column groups and merged cells included — rather than retyping it. Each deliverable is matched to the real document when it's uploaded, and late, due, at-risk, slipped and issued are worked out automatically. A chase list groups late items by firm and exports to Excel, and dashboards show delivery against the plan for every firm.
A TIDP is just a firm's promise about what it'll deliver and when. The MIDP is the main contractor keeping score. Keep the baseline fixed, let the documents tick themselves off, and chase by firm — and the plan becomes the early warning it was meant to be.
What is a TIDP?
A task information delivery plan (TIDP) is a task team's plan of the information it will produce for a project: each information container, who authors it, its level of information need, its dependencies, how long it will take, and when it will be delivered at each milestone. Every task team — each consultant or design-and-build subcontractor — prepares one.
What is the MIDP?
The master information delivery plan (MIDP) is the lead appointed party's combined plan, built by aggregating every task team's TIDP and checking the dependencies between them and the review periods needed by the main contractor and the client. On most projects the main contractor prepares and maintains it.
Who is responsible for the MIDP?
The lead appointed party — usually the main contractor once appointed. It aggregates the TIDPs, baselines the deliverables and dates, tells task teams about changes, and records risks to delivery. The MIDP forms part of the lead appointed party's appointment, and each TIDP forms part of its task team's appointment.
What is level of information need?
Level of information need defines how much information a deliverable must contain for its purpose — its geometry, its alphanumerical data and its documentation. The current standard for it is ISO 7817-1:2024, which replaced EN 17412-1.
How often should the MIDP be updated?
Whenever scope or dates change, and at least as often as you report progress. The baseline should stay fixed so you can see slippage; the current forecast and actual delivery dates are what change. An MIDP that's only updated for the monthly report is a record of the past, not a plan.
Stephen Mckenna MCIOB
30+ years in UK commercial construction, from site management to director level. Now building the project management tools he wished he'd had.
Tier-one contractor processes shouldn't only be available to tier-one contractors. Drawing registers, document control, RFIs, programmes, financial tracking — built for how you actually run projects. One platform, every module, every user — priced to your business. Leave your email and we'll show you round.
By subscribing, you agree to our Privacy Policy.
A UK comparison of document control and common data environment (CDE) software — Construction AI, Asite, Viewpoint For Projects, Autodesk Forma, Procore, Dalux and Thinkproject — on ISO 19650 claims, naming and suitability codes, review workflows, stamps, delivery plans and guest access.
ISO 19650 reads like it was written for information managers, but main contractors carry most of it. Here's what it actually asks of you — CDE states, naming, status and revision codes, and who's responsible for what — in plain English.
You can't build it all yourself, and the subcontractors you rely on are the ones most likely to sink your programme. Here's how to run packages so they deliver.