Building a Schedule of Rates That Wins Tenders and Doesn't Lose Money

Your rate book is the most reused document in the business, and usually the least maintained. Here's how to build a rate properly from labour, materials and plant, keep the book current, derive star rates, and stop stale rates quietly eroding your margin.

SMStephen Mckenna MCIOB
6 minutes read

Building a Schedule of Rates That Wins Tenders and Doesn't Lose Money

Every estimator has a rate book. Most inherited it. It's a spreadsheet, or a few spreadsheets, built years ago by someone who's since left, with rates for everything from blockwork to skirting. Some rates were built up properly. Some were typed in from a tender that went well. Nobody's quite sure which.

It's the most reused document in the business, and usually the least maintained. Every tender takes its rates from it, so if a rate is wrong, every tender gets it wrong. Here's how to build one that you can trust.

What a schedule of rates is

The term covers two related things:

  • A client's schedule of rates, used to price term and maintenance contracts. The contractor tenders a percentage adjustment or its own rates, and work is ordered and valued against the schedule as it arises.
  • A contractor's or subcontractor's own schedule of rates, often called a rate book: the priced basis for estimating, reused across tenders.

This guide is mostly about the second. The principles apply to both.

Building up a rate

A rate you can trust is one you can take apart. Every rate should be built from its components:

1. Labour. The all-in labour rate for the gang (see below) divided by its output: how many square metres, metres or items it produces per hour.

Two-person gang at £38.50 per hour each (all-in) = £77.00 per hour Output: 1.6 m² per gang hour Labour per m² = £77.00 ÷ 1.6 = £48.13

2. Materials. The quantity per unit, at the current price, plus waste (cutting, breakage, overlaps) and delivery.

3. Plant. Mixers, access, tools, hire, spread across the units it serves.

4. Subcontract. Where part of the item is sublet, its rate.

5. Overheads and profit. Decide whether these go into each rate or are added once to the whole tender. Either works. Mixing the two, so some rates include them and some don't, doesn't.

Record every component. When a client queries a rate, or a variation needs a new one, you'll need to show how you got there.

The all-in labour rate

The most common way to under-price work is to use the wage instead of the cost of the operative. An all-in rate includes:

  • basic pay;
  • employer's National Insurance and pension contributions;
  • holiday pay and bank holidays;
  • allowances (travel, tool, bonus);
  • CITB levy, where it applies;
  • sick pay;
  • PPE, training and supervision;
  • non-productive time: weather, waiting, travel between jobs.

Build it once, properly, for each grade, and review it every time a wage agreement or a statutory rate changes.

Outputs: where rates go right or wrong

The output assumption is where most of a rate's accuracy lives. A rate built on an output the gang achieves on an open, repetitive floor plate will lose money on a cut-up refurbishment. So:

  • Record the conditions an output assumes: new build or refurb, height, access, repetition.
  • Check outputs against site. Compare tendered outputs with what timesheets and progress actually show, and update the book.
  • Adjust per project, not by editing the master rate. A project factor for difficulty or location is cleaner than a dozen quietly edited rates.

Keeping the book current

  • Date every rate, and when it was last reviewed.
  • Flag stale rates: anything not reviewed for, say, twelve months.
  • Review after every significant tender, won or lost. A rate that keeps losing work may be too high; one that keeps winning by a mile may be too low.
  • Keep regional or annual versions side by side rather than overwriting, so you can see what changed.
  • Note the source of every material price: supplier, quote, date.

Star rates

A star rate is a new rate for an item that isn't in the schedule or the bill. They come up constantly in variations and term contracts. The fair way to derive one:

  1. Find the nearest similar rates in the schedule.
  2. Identify the difference: more labour, a different material, extra plant.
  3. Adjust the similar rate for the difference, or build the new rate from first principles using the same labour rates and outputs.
  4. Record the basis, so the other side can check it.

Our guide to valuing variations properly covers how star rates fit into variation valuation.

Using the book on a tender

  • Match carefully. A bill item described differently from your rate book item may be the same work, or may not. Check the description and the measurement rules, not just the name.
  • Check the units. A rate per m² applied to an item measured per metre is a classic error.
  • Price the preliminaries separately. Site-wide costs don't belong in measured rates; our guide to pricing preliminaries covers them.
  • Review the totals. A package that comes out wildly different from similar recent jobs deserves a second look before it goes out. Our guide to writing a winning tender covers the rest.

How Construction AI handles it

At Construction AI, rate books live in the Library, with an optional build-up behind each rate, and import and export to Excel. A rate co-pilot sits alongside the book: it makes bulk adjustments ("copper up 2%"), derives a star rate for a missing item from similar items, assesses competitiveness against built-in benchmarks, and finds stale rates. When you price a tender, Match Rates matches each item in the pricing schedule to your rate book by meaning, with a confidence score, and you tick which matches to apply.

A rate book is only as good as its weakest rate, and you never know which one that is until it's cost you a job. Build every rate from its parts, date it, and check it against what site actually achieves.

Frequently asked questions

What is a schedule of rates in construction?

A schedule of rates is a list of work items with a unit rate for each — per square metre, per metre, per item. Clients use them to price term and maintenance contracts, where work is ordered and valued against the schedule. Contractors and subcontractors keep their own internal schedule of rates, often called a rate book, as the priced basis for estimating.

How do you build up a unit rate?

Start with the labour: the all-in hourly cost of the gang divided by its output per unit. Add the materials per unit, including waste and delivery. Add plant per unit, and any subcontract element. Then decide whether overheads and profit go into each rate or are added once at the end. Record each component, so the rate can be checked, adjusted and defended later.

What is an all-in labour rate?

The full hourly cost of employing an operative, not just the wage: basic pay, employer's National Insurance and pension contributions, holiday pay and bank holidays, allowances, CITB levy where it applies, sick pay, travel, PPE and non-productive time. It's usually well above the basic hourly wage, and using the basic wage in a rate is one of the commonest ways to under-price work.

What is a star rate?

A star rate is a new rate for an item that isn't in the schedule or bill. It's usually derived from the nearest similar rates, adjusted for the difference in labour, materials or plant, or built up from first principles. Star rates are common in variations and in term contracts when work arises that the schedule didn't foresee.

How often should a rate book be updated?

At least once a year, and whenever a major cost changes — a wage agreement, a materials price rise, a new supplier. Date every rate, flag rates that haven't been reviewed for a set period, and check rates that keep winning or losing work against recent tender results and actual site outputs.

SM

Stephen Mckenna MCIOB

30+ years in UK commercial construction, from site management to director level. Now building the project management tools he wished he'd had.

Stop losing money on problems you can see coming

Tier-one contractor processes shouldn't only be available to tier-one contractors. Drawing registers, document control, RFIs, programmes, financial tracking — built for how you actually run projects. One platform, every module, every user — priced to your business. Leave your email and we'll show you round.

By subscribing, you agree to our Privacy Policy.

Run the next job on it.

Tier-one processes for the whole business. One platform, every module, every user, priced to your business.