The Design Responsibility Matrix: Who Designs What, and How to Stop the Gaps

Most design disputes aren't about bad design. They're about design nobody thought was theirs. Here's what a design responsibility matrix is, how to build one that works, the gaps that keep turning up, and how to flow it down to subcontractors.

SMStephen Mckenna MCIOB
6 minutes read

The Design Responsibility Matrix: Who Designs What, and How to Stop the Gaps

Ask who designed the fire stopping around the risers, and you'll usually get three answers. The architect says it's a performance specification and the detail is the contractor's. The M&E subcontractor says it's builders' work. The drylining subcontractor says it's not in their scope. Meanwhile the inspector is waiting, the ceilings are on hold, and nobody's priced it.

That isn't a design failure. It's a responsibility failure. The design was never anyone's, because nobody wrote down whose it was.

A design responsibility matrix (DRM) is how you write it down. Done well, it's one of the most valuable documents on a design and build project. Done badly, or not at all, the gaps turn into delays and disputes on site.

What a DRM is

A DRM is a table. Down the side are design activities: the frame, the connections, the cladding brackets, the drainage, the fire strategy details, the BWIC holes. Across the top are the parties: typically the architect, the structural engineer, the M&E engineer, any specialist designers, the main contractor and the subcontractors. In each cell is a code saying what that party's responsibility is for that activity.

Most DRMs have two parts:

  1. General definitions. What "design" means on this project, what each code means, and what each stage of design (concept, developed, technical, fabrication) involves. These sit at the top and apply to everything.
  2. A matrix per package. For each trade package, the specific design activities and who owns each one.

Why it matters more than it used to

  • Design and build is the norm. On most projects the main contractor takes on design responsibility for some or all of the works: the Contractor's Designed Portion under a JCT contract, or the whole design under design and build. That responsibility then has to be passed down to consultants and subcontractors, without gaps.
  • Subcontractors design more. Curtain walling, steel connections, M&E installations, piling and temporary works are routinely designed by specialists. Each one needs a clear boundary.
  • Building safety. Since October 2023, building regulations in England place duties on everyone who designs building work, and on the principal designer and principal contractor for building regulations, to plan, manage and coordinate design so that the work complies. Knowing exactly who designed what is part of showing that was done. Our guide to the golden thread under the Building Safety Act covers the wider picture, and our guide to principal designer duties under CDM 2015 covers the health and safety side.

Codes: keep them simple

Firms use different codes. A simple, common approach:

CodeMeans
1Primary responsibility: this party produces the design and is accountable for it
2Secondary responsibility: this party contributes information or reviews, but doesn't own it
N/ANot applicable: this party has no involvement
–Not yet decided

Whatever codes you choose, three rules:

  1. Define them in the general definitions, so nobody has to guess.
  2. Exactly one primary per activity. Two 1s on a row is an overlap. No 1 is a gap.
  3. Never leave a "not yet decided" at contract. A dash at tender is a question. A dash in a signed subcontract is a dispute waiting to happen.

The gaps that keep turning up

The same activities fall between packages on project after project. List them explicitly, every time:

  • Builders' work in connection with services: holes, sleeves, plinths, bases and supports.
  • Fire stopping and cavity barriers, especially around services penetrations.
  • Interfaces between frame and envelope: brackets, fixings, tolerances, movement.
  • Secondary steel for plant, signage, canopies and services.
  • Steel connection design where the engineer has designed members but not connections.
  • Temporary works: propping, back-propping, excavation support and crane bases.
  • Below-ground drainage and its connection to services inside the building.
  • Movement joints across packages.
  • Services coordination in ceiling voids and risers: who produces the coordinated drawings, and who resolves clashes.
  • Setting out and dimensional coordination between trades.

If any of these is missing from your matrix, ask whose it is before you price.

How to build one that works

  1. Start at tender. Build the DRM from the client's design responsibility schedule, the specification and the drawings. Gaps found at tender can be priced or qualified; gaps found on site can't. Our guide to tender qualifications covers how to flag what's unclear.
  2. Work package by package. List the design activities for each trade, not just the headline elements. "Curtain walling" isn't an activity; "bracket design and fixing to the slab edge" is.
  3. Check every row has exactly one primary.
  4. Check across packages, not just within them. The interface activities above live between packages, so check them with both sides.
  5. Send each package's DRM with the enquiry, so subcontractors price the design they're taking on and say if they disagree.
  6. Agree it before award, and attach it to the subcontract with the scope of works.
  7. Update it when things change, at novation of the design team, at each design stage, and when a variation moves design responsibility.

How Construction AI handles it

At Construction AI, the DRM lives in the Library. General definitions sit at the top, then a matrix per package: one row per design activity, with 1, 2, N/A or – for each of six parties — architect, structural engineer, M&E engineer, specialist, main contractor and subcontractor. It exports to Excel. In each tender package, the DRM sits alongside the scope of works and the pricing schedule in the enquiry, and can be exported to Excel and re-imported, so subcontractors price against the same matrix you'll put in their order. The AI DRM writer drafts the general definitions and the activities for a package from built-in reference content, for you to review and adjust.

Design disputes are rarely about whether the design was good. They're about whose it was. Write it down, one owner per activity, before anyone prices it.

Frequently asked questions

What is a design responsibility matrix?

A design responsibility matrix (DRM) is a table that sets out, for each design activity on a project, which party is responsible for it — typically the architect, structural engineer, M&E engineer, specialist designers, the main contractor and the subcontractors. It usually starts with general definitions of what each level of design means, then lists activities package by package so that every piece of design has an owner.

Why do contractors need a DRM?

Because on design and build projects, and wherever subcontractors design part of the works, responsibility is split across many parties. Without a matrix, gaps (design nobody does) and overlaps (design two parties think is theirs) only show up on site, as delays, extra cost and disputes. A DRM agreed at tender, and attached to each subcontract, makes those splits explicit before anyone prices or builds.

What do the codes in a DRM mean?

Codes vary by firm. A common approach is "1" for the party with primary responsibility for an activity, "2" for a party with a secondary or contributing role, and "N/A" or a dash where a party has no involvement. Whatever codes you use, define them at the top of the matrix and use them the same way on every package.

Where do design gaps usually occur?

At interfaces between packages and between design and construction: builders' work in connection with services, fire stopping and cavity barriers, interfaces between the frame and the envelope, secondary steel and fixings, temporary works, below-ground drainage, movement joints, and coordination of services in ceiling voids. These are the activities to list explicitly in every DRM.

Should the DRM go into the subcontract?

Yes. A DRM only protects you if it's part of the contract. Include the package's DRM in the tender enquiry so subcontractors price the design they're taking on, and attach the agreed version to the subcontract order alongside the scope of works.

SM

Stephen Mckenna MCIOB

30+ years in UK commercial construction, from site management to director level. Now building the project management tools he wished he'd had.

Stop losing money on problems you can see coming

Tier-one contractor processes shouldn't only be available to tier-one contractors. Drawing registers, document control, RFIs, programmes, financial tracking — built for how you actually run projects. One platform, every module, every user — priced to your business. Leave your email and we'll show you round.