Most subcontract disputes start with a scope that said 'the works' and assumed everyone knew what that meant. Here's how to structure a scope of works, what every package scope should cover, the phrases that cause trouble, and how to keep scopes consistent across packages.
"Supply and install all drylining works in accordance with the drawings and specification."
That's a scope of works on more projects than anyone would like to admit. It feels complete, because the drawings and specification say what's needed. Then the job starts, and the questions come. Who does the bulkheads? The access panels? The fire-stopping at the head of the partitions? The patching after the electricians? Who provides the scaffold towers, takes the waste away, and produces the O&Ms?
Each of those questions is a variation claim, a contra charge or a delay waiting to happen. A good scope answers them before the subcontractor prices.
The most useful structural decision you can make is to split the scope into two layers:
The general layer saves you rewriting the same clauses twenty times, and stops them drifting between packages. The package layer is where the real thought goes.
The real test of a scope isn't one package on its own. It's whether every package together covers the whole job, with nothing missed and nothing double-counted. Three checks:
Then send the scope with the enquiry, ask tenderers to list their own exclusions and qualifications, and close the gaps before award. Our guides to comparing subcontractor bids and tender qualifications cover that step.
At Construction AI, scopes of works live in the Library in two layers: a general scope that sits on top of every trade package's scope, and a scope for each package, with clauses edited in place and notes against them. Scopes export to Excel. In each tender package, the scope goes out with the enquiry alongside the DRM and the pricing schedule, so every tenderer prices the same document. The AI scope writer drafts general and package scopes from built-in reference scope content, for you to review, edit and adopt as your own.
A scope of works is a list of answers to questions the subcontractor would otherwise ask on site. Ask them yourself, at tender, and write the answers down.
What is a subcontract scope of works?
A subcontract scope of works is the document that sets out exactly what a subcontractor will provide: the work included, the standards it must meet, the design responsibility it carries, what's excluded, the interfaces with other trades, and the testing, documentation and handover it must deliver. Together with the drawings, specification and subcontract conditions, it defines what the subcontract price covers.
What is the difference between a general scope and a package scope?
A general scope sets out the requirements that apply to every subcontractor on the project — site rules, working hours, health and safety, cleaning and waste, programme, quality, documentation and handover. A package scope sets out the requirements specific to one trade. Keeping the general requirements in one document, sent with every package, means they're consistent and you don't have to rewrite them twenty times.
Should a scope of works list exclusions?
Yes. Listing what's excluded, and who provides it instead, is as important as listing what's included. An exclusion with no named alternative is a gap. Ask tenderers to state their own exclusions too, so you can level bids and close the gaps before award.
Are "deemed to include" clauses enforceable?
They can be, but they're a weak substitute for a clear scope. Broad wording like "everything necessary to complete the works" invites argument about what was reasonably foreseeable and what was priced. It's far better to list the items you expect the subcontractor to provide than to rely on a catch-all.
What should be attached to a scope of works?
The drawings and specification sections the scope relies on, listed by number and revision; the design responsibility matrix for the package; the attendances schedule saying who provides what on site; the programme or key dates; and the pricing schedule the subcontractor prices against.
Stephen Mckenna MCIOB
30+ years in UK commercial construction, from site management to director level. Now building the project management tools he wished he'd had.
Tier-one contractor processes shouldn't only be available to tier-one contractors. Drawing registers, document control, RFIs, programmes, financial tracking — built for how you actually run projects. One platform, every module, every user — priced to your business. Leave your email and we'll show you round.
By subscribing, you agree to our Privacy Policy.
Delay claims are won on records made at the time, not on recollections a year later. Here's which records carry weight, how emails and programme updates should be kept, what notices you can't afford to miss, and how to build the record as you go.
Most design disputes aren't about bad design. They're about design nobody thought was theirs. Here's what a design responsibility matrix is, how to build one that works, the gaps that keep turning up, and how to flow it down to subcontractors.
A delay you can't demonstrate is a delay you'll pay for. Here's how as-planned versus as-built analysis turns 'we were late because of you' into an entitlement you can defend.
Tier-one processes for the whole business. One platform, every module, every user, priced to your business.