Payment Notices and Pay Less Notices: A Main Contractor's Guide to Getting Them Right

Miss a payment notice or a pay less notice and you can be forced to pay a subcontractor's application in full, whatever the work was worth. Here's the timetable, what each notice must say, the mistakes that invalidate them, and a routine that keeps you safe every month.

SMStephen Mckenna MCIOB
7 minutes read

Payment Notices and Pay Less Notices: A Main Contractor's Guide to Getting Them Right

Most of what's written about the Construction Act's payment rules is written for the party being paid. That makes sense: the rules exist to protect subcontractors' cash flow. But the people who actually have to issue the notices, every month, for every package, are main contractors' QSs. And when the notices go wrong, it's the main contractor who pays.

Get a notice late, or vague, and you can find yourself obliged to pay a subcontractor's application in full, even when you know the work isn't worth it. This guide is written for the paying side: what the notices are, when they're due, what they must say, and how to make sure they go out right every time.

If you're on the receiving end, our guide to payment applications under the Construction Act covers the payee's side.

The two notices, in plain English

The Housing Grants, Construction and Regeneration Act 1996, as amended in 2011 (the Construction Act), sets up a simple sequence for each payment:

  1. The payment due date. When the payment becomes due, usually set by reference to the application.
  2. The payment notice. The payer says how much it considers due at the due date, and how that figure was worked out.
  3. The pay less notice. If the payer intends to pay less than the notified sum, it says so, with the sum it now considers due and how it was worked out.
  4. The final date for payment. The last day on which payment can be made.

The notified sum is the figure everything turns on. It's the amount in the payment notice. If no valid payment notice was given, it's the amount in the payee's application (or a default notice the payee gives).

Unless a valid pay less notice is given in time, the notified sum must be paid by the final date for payment. That's the rule that catches contractors out.

The timetable

The Act itself requires the payment notice no later than five days after the payment due date. For the other dates, your subcontract should set them. If it doesn't, or its terms don't comply with the Act, the Scheme for Construction Contracts fills the gap. Under the Scheme:

  • The final date for payment is 17 days after the payment due date.
  • The pay less notice must be given no later than seven days before the final date for payment.

Many subcontracts change these periods, and amended terms often shorten the window for a pay less notice. Read the subcontract, not the Scheme, and put the actual dates in the diary for every package.

What a payment notice must say

  • The sum you consider due at the payment due date.
  • The basis on which it's calculated. Enough detail that the subcontractor can see how you got there: measured work, variations, materials, retention, previous payments.

A payment notice is required even if you think nothing is due. A notice of £0, with the basis, is still a valid notice. Silence isn't.

What a pay less notice must say

  • The sum you now consider due on the date the notice is given.
  • The basis on which that sum is calculated.

The courts expect a pay less notice to be clear enough that the subcontractor can understand what's being deducted and why. "Less contra charges as discussed" isn't a basis. "Less £3,850 for 70 hours of cleaning labour at £55 per hour, removing the drylining contractor's waste from levels 2 to 4 between 2 and 13 June, as recorded in the attached daywork sheets" is. Our guide to contra charges covers how to build a deduction that will stand up.

The mistakes that cost contractors money

  1. Missing the date. A pay less notice a day late is not a pay less notice. The notified sum stands.
  2. No payment notice at all. The subcontractor's application becomes the notified sum, and you're relying entirely on a pay less notice to get out of it.
  3. No basis of calculation. A figure with no explanation risks being found invalid.
  4. Sent to the wrong place. If the subcontract says how notices must be served, follow it. An email to a site foreman may not count.
  5. A payment notice that can't be told from a valuation. Label notices clearly for what they are, with the application they respond to.
  6. Withholding without a notice. Deducting a contra charge, or simply paying less, without a valid pay less notice is a common route to a quick adjudication you'll lose.

Smash and grab, and why "pay now, argue later" is the law

If you fail to give a valid notice, the subcontractor can start a "smash and grab" adjudication: it doesn't argue about the value of the work, only that you didn't serve the notices, so the notified sum is payable. These adjudications are quick, cheap for the claimant and hard to defend.

You might think the answer is to start your own adjudication on the true value of the work. The Court of Appeal settled this in S&T (UK) Ltd v Grove Developments Ltd (2018): the paying party must pay the notified sum first. Only then can it pursue a "true value" adjudication, which corrects the position going forward. You can't use a true value claim to avoid paying a notified sum you failed to challenge in time.

So the cost of a missed notice isn't just the overpayment. It's the cash out of your account now, and the cost of getting it back later.

A monthly routine that keeps you safe

  1. Diarise every date for every package when the subcontract is signed: due date, payment notice deadline, pay less deadline, final date.
  2. Issue a payment notice for every application, every time, even if the figure is the same as last month or zero.
  3. Value against the application line by line, so the basis of your figure is the same structure as theirs.
  4. Decide on deductions before the pay less deadline, not on the final date for payment. Build in a margin of a working day or two.
  5. Use the subcontract's method of service, and keep proof of when each notice was sent.
  6. Keep the evidence with the notice. Daywork sheets, photos, the instruction, the measurement: attach it or reference it.
  7. Record what you certified and what you paid, so next month's valuation starts from the right place.

How Construction AI handles it

At Construction AI, subcontract applications are valued line by line, and the payment notice or pay less notice is built from that valuation, with structured reasons and reason codes for every deduction. One click generates the notice as a PDF, emails it to the subcontractor and records the matching cost in the purchase ledger, net of retention and with CIS and VAT applied, so the commercial position and the notice can't drift apart. On the client side, each main contract application carries its statutory dates — application, due date, payment notice, pay less notice and final date — with countdowns, so the deadlines that matter are always in front of you.

The Construction Act rewards the organised. Issue every notice, on time, with the basis spelled out, and the rules work for you rather than against you.

Frequently asked questions

What is a pay less notice?

A pay less notice is the notice a paying party must give under the Construction Act if it intends to pay less than the notified sum — the amount in the payment notice, or, if no payment notice was given, the amount in the payee's application. It must state the sum the payer considers due and the basis on which that sum is calculated, and it must be given no later than the prescribed period before the final date for payment.

When must a pay less notice be issued?

No later than the period before the final date for payment that the contract sets. If the contract doesn't set one, or isn't compliant with the Act, the Scheme for Construction Contracts applies and the period is seven days before the final date for payment. Check your own subcontract: amended terms often change it.

What happens if I don't issue a payment notice?

If the payer doesn't give a payment notice on time, the payee's application (or a notice the payee gives in default) becomes the notified sum. Unless a valid pay less notice is given in time, that sum must be paid by the final date for payment — even if the work is worth less.

Can I start a true value adjudication instead of paying?

Not as a way of avoiding payment. The Court of Appeal held in S&T (UK) Ltd v Grove Developments (2018) that the paying party must pay the notified sum first. Only then can it pursue an adjudication on the true value of the work, which corrects the position for the future.

What must a payment notice contain?

The sum the payer considers due at the payment due date, and the basis on which that sum is calculated. A payment notice must be given even if the sum considered due is zero. The Act requires it no later than five days after the payment due date.

SM

Stephen Mckenna MCIOB

30+ years in UK commercial construction, from site management to director level. Now building the project management tools he wished he'd had.

Stop losing money on problems you can see coming

Tier-one contractor processes shouldn't only be available to tier-one contractors. Drawing registers, document control, RFIs, programmes, financial tracking — built for how you actually run projects. One platform, every module, every user — priced to your business. Leave your email and we'll show you round.